Tulip

Completed

Nagpur (M Corp.), Nagpur 440001 |Promoter: Leverage Infrastructures Private Limited

Residential / Group HousingRERAP50500001330
27 Jul 2017Registered with MahaRERA
31 Mar 2019Promised completion
3Buildings
73Units registered
1MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
3
Unit types
3 BHK, 1 BHK, 2 BHK73 units in all
Land area for this project
4,284 sq m (46,113 sq ft)
Permissible built-up area
6,699 sq m (72,107 sq ft)
Sanctioned built-up area
6,699 sq m (72,107 sq ft)
Address
Kh No 174/1, Plot No. 39PIN 440001
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.50524, 73.76611
Tulip is at latitude 18.50524, longitude 73.76611.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2019

The latest completion date on record passed 7 years and 7 months ago.

Registered
27 Jul 2017
Promised
31 Mar 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050000133027 Jul 201731 Mar 2019—Leverage Infrastructures Private LimitedProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Block - 1724
Block - 2724
Block - 3825

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

73 units registered

3 BHK · 48 units1 BHK · 1 unit2 BHK · 24 units
BuildingTypeCarpet areaUnits
Block - 13 BHK83 sq m · 893 sq ft12
Block - 13 BHK83 sq m · 893 sq ft12
Block - 23 BHK83 sq m · 893 sq ft12
Block - 23 BHK83 sq m · 893 sq ft12
Block - 31 BHK42 sq m · 452 sq ft1
Block - 32 BHK65 sq m · 700 sq ft6
Block - 32 BHK66 sq m · 710 sq ft12
Block - 32 BHK68 sq m · 732 sq ft6

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Block - 1Closed/Covered00008
Block - 1Open Space000076
Block - 2Closed/Covered00008
Block - 2Open Space000077
Block - 3Closed/Covered00006
Block - 3Open Space000083

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Block - 1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Block - 2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Block - 3

  • Excavation90%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyIT SHALL BE PROVIDED AFTER COMPLETION OF PROJECT100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEWER LINE WILL BE CONNECTED TO THE MAIN SEWER LIN100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingAS PER MAP100%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER MAP100%
  • Energy managemcntAS PER MAP100%
  • Fire protection and fire safety requirementsAS PER MAP100%
  • Electrical meter room, sub-station, receiving stationNO SUB STATION ONLY ELECTRIC PANEL BOARD100%
  • Aggregate area of recreational Open SpaceONLY ELECTRIC PANEL BOARDNot applicable
  • Open ParkingAS PER MAP100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

16 documents held by Deedo, 31 filings listed on MahaRERA's project page

Form b

Title

Registration certificate

Others

Allotment letter

Layout plans

Building plans

Document library

  • Declaration in FORM BForm B.pdf · uploaded 22 Jul 2017View
  • Commencement Certificates / NA Order for plotted development39 Permit.pdf · uploaded 22 Jul 2017Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architech Form 1.pdf · uploaded 22 Jul 2017Source
  • Details of encumbrancesNon Encrumbance.pdf · uploaded 22 Jul 2017Source
  • Copy of the legal title reportSearch Report.pdf · uploaded 22 Jul 2017View
  • Building Plan Approval (IOD)1.pdf · uploaded 22 Jul 2017View
  • Building Plan Approval (IOD)2.pdf · uploaded 22 Jul 2017View
  • Building Plan Approval (IOD)3.pdf · uploaded 22 Jul 2017View
  • Building Plan Approval (IOD)4.pdf · uploaded 22 Jul 2017View
  • Building Plan Approval (IOD)5.pdf · uploaded 22 Jul 2017View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 24 Jul 2017Source
  • Proforma of Allotment letterSample Agreement.pdf · uploaded 24 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 25 Jul 2017Source
  • Copy of Layout Approval (in case of layout)Layout map.pdf · uploaded 25 Jul 2017View
  • Copy of Layout Approval (in case of layout)Release Letter.pdf · uploaded 25 Jul 2017View
  • Certificates of Architect (Form 4)Architect Certificate.pdf · uploaded 15 Dec 2018Source
  • Certificates of CA (Form 5)Form 5.pdf · uploaded 19 Jul 2019Source
  • Other39 - Occupancy Certificate.pdf · uploaded 16 Sep 2019View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Handing Over Letter.pdf · uploaded 16 Sep 2019Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 8 Oct 2021Source

Promoter documents

  • Declaration Form BForm B.pdf · uploaded 22 Jul 2017View
  • Legal Title reportSearch Report.pdf · uploaded 22 Jul 2017View

Technical documents

  • Layout ApprovalLayout map.pdfView
  • Layout ApprovalRelease Letter.pdfView
  • Building Plan Approval1.pdfView
  • Building Plan Approval2.pdfView
  • Building Plan Approval3.pdfView
  • Building Plan Approval4.pdfView
  • Building Plan Approval5.pdfView

Other legal documents

  • Other39 - Occupancy Certificate.pdfView

Proforma allotment letter

  • Proforma allotment letterSample Agreement.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nagpur (M Corp.), Nagpur (Urban) taluka

Survey, CTS, gat or plot numbers

39KH NO 174/1PLOT NO. 39

As published on MahaRERA's project page

KH NO 174/1, PLOT NO. 39

Boundaries

North
Amenity Space 1
South
Plot No 38
East
12 Mtr Road
West
Others Plot

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrashant Baliram Satpute—

Source: MahaRERA project page. Contact details are not shown.