Kush Buildcon Llp

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%2 of 4 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kush PrestigeP51800002724Andheri2017Not reported31 Dec 2017—On date
Kush SapphireP51800007193Andheri2017Not reported31 Dec 2018—On date
Kush SolitaireP51800028906Borivali2021Not reported30 Dec 202329 Dec 2024+12 months
Kush SymphonyP51800030410Kurla2021Not reported31 Dec 202330 Jun 2025+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kush PrestigeOn date
  • Kush SapphireOn date
  • Kush Solitaire+12 mo
  • Kush Symphony+18 mo

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Kush Symphony (P51800030410).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology