Kush Solitaire
Certificate SignedBorivali, Mumbai Suburban 400097 |Promoter: Kush Buildcon LLP
Project summary
As registered with MahaRERA
- Buildings
- 1
Location
Coordinates as published by MahaRERA
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
The latest completion date on record passed 1 year and 10 months ago.
- Registered
- 7 Apr 2021
- Promised
- 30 Dec 2023
- Revised
- 29 Dec 2024
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51800028906 | 7 Apr 2021 | 30 Dec 2023 | 29 Dec 2024 | Kush Buildcon LLP | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Kush Solitaire | 10 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Borivali
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.