Kumar Company
Company or firm · 4 projects · 4 MahaRERA registrations
Also appears as Kumar Construction and Properties Pvt Ltd
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Pebble Park D1P52100000073 | Hadapsar | 2017 | Not reported | 30 Oct 2020 | — | On date |
| Selena BP52100000252 | Pashan | 2017 | Not reported | 30 Mar 2019 | — | On date |
| Princeville - B3 and C1P52100000755 | Pimpri Chinchawad (M Corp.) | 2017 | Not reported | 31 May 2019 | — | On date |
| PiccadillyP52100003854 | Wakad | 2017 | Not reported | 31 Dec 2018 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology