Jitu Properties & Developments Pvt Ltd

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Galaxy CityP52100001605Lonavala (M Cl)2017Not reported31 May 201830 Dec 2022+55 months
Charudatta AparmentsP52100019012Lonavala (M Cl)2018Not reported16 Nov 2020—On date
Royal ParkP52100027378Lonavala (M Cl)2020Not reported30 Apr 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Galaxy City+55 mo
  • Charudatta AparmentsOn date
  • Royal ParkOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 55 months, for Galaxy City (P52100001605).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology