Jagrutsara Structures Llp
Company or firm · 22 projects · 24 MahaRERA registrations
Also appears as Sara Builders & Developers
22Projects24 RERA registrations
0Completedas reported on MahaRERA project pages
85%Kept RERA date11 of 13 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 9 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sara Parivartan - Sector EP51500001935 | Sawangi | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Sara SanskrutiP52100013952 | Kharabwadi (Ct) | 2017 | Certificate Signed | 30 Sep 2022 | 30 Sep 2022 | On date |
| Signature 28P52100015061 | Kharabwadi (Ct) | 2018 | Certificate Signed | 30 Dec 2020 | 31 May 2023 | +29 months |
| Sara City C11P52100015547 | Kharabwadi (Ct) | 2018 | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| Sara City C9P52100015625 | Khed | 2018 | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| Sara City C10P52100015649 | Kharabwadi (Ct) | 2018 | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| Sara City C8P52100015654 | Kharabwadi (Ct) | 2018 | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| Sara Business CenterP52100017190 | Kharabwadi (Ct) | 2018 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Sara SwapnaviharP52100019508 | Khed | 2019 | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +4 months |
| Sara SwapnodayP52100029638 | Kharabwadi (Ct) | 2021 | Certificate Signed | 29 Jun 2026 | 29 Jun 2026 | On date |
| Sara City C4P52100032305 | Kharabwadi (Ct) | 2021 | Certificate Signed | 30 Dec 2027 | 30 Apr 2028 | +4 months |
| Sara City C5P52100032660 | Khed | 2022 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Sara Kasturi Building BP52100032693 | Khed | 2022 | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Sara Abhiman PlotsP52100046676 | Kharabwadi (Ct) | 2022 | Certificate Signed | 31 Mar 2023 | 31 Mar 2023 | On date |
| Sara AbhimanP52100046745 | Khed | 2022 | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Sara KasturiP52100049278 | Khed | 2023 | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| Sara NilaayP52100056337 | Nanekarwadi (Ct) | 2024 | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 months |
| Sara City Plot E 1P52100056494 | Kharabwadi (Ct) | 2024 | Certificate Signed | 31 Dec 2029 | 31 Dec 2029 | On date |
| Sara KasturiP52100076943 | Khed | 2024 | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 months |
| Sara City Tower C2P52100079907 | Kharabwadi (Ct) | 2025 | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 months |
| Sara OasisPR1260002501529 | Moshi | 2025 | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
| Sara NilaayPR1261012501602 | Nanekarwadi (Ct) | 2025 | Certificate Signed | 31 Mar 2031 | 31 Jul 2031 | +4 months |
| Sara City Tower C3PR1263032502478 | Kharabwadi (Ct) | 2026 | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 months |
| Sara Kasturi Building CPR1261012600183 | Chakan (Ct) | 2026 | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 months |
Show all 24 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 24 registrations
Track record notes
- 11 of 13 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 29 months, for Signature 28 (P52100015061).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology