Horizon Projects Pvt Ltd
Company or firm · 11 projects · 11 MahaRERA registrations
Also appears as Horizon Projects Private Limited
11Projects11 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 6 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| My City - Phase I - Part IP51700000528 | Dombivli | 2017 | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 months |
| My City - Phase I - Part IIIP51700005477 | Dombivli | 2017 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| My City - Phase II - Cluster 4P51700008440 | Usarghar | 2017 | Certificate Signed | 30 Dec 2028 | 30 Dec 2028 | On date |
| My City - Phase I - Part IIP51700009168 | Dombivli | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| My City- Phase II -Cluster 05 - Part IP51700019085 | Usarghar | 2019 | Certificate Signed | 30 Mar 2025 | 30 Mar 2025 | On date |
| My City Phase II Cluster 5 Part IIIP51700027171 | Usarghar | 2020 | Certificate Signed | 30 Jun 2027 | 30 Jun 2027 | On date |
| My City Phase II Cluster 5 Part IIP51700032157 | Usarghar | 2021 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| Runwal Garden City Cluster 6 Tower 6 to 9P51700052561 | Usarghar | 2023 | Certificate Signed | 31 Mar 2029 | 31 Mar 2029 | On date |
| Runwal Shopping Arcade 2 - R Galleria 2P51700078830 | Usarghar | 2025 | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 months |
| RGC Runwal My City EWS - LIG BuildingP51700079091 | Usarghar | 2025 | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 months |
| Runwal Garden City Cluster 11 Tower 1-2PR1337072502636 | Usarghar | 2026 | Certificate Signed | 18 Jul 2032 | 18 Nov 2032 | +4 months |
Show all 11 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 11 registrations
Track record notes
- 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for My City - Phase I - Part I (P51700000528).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology