Company or firm · first RERA registration 2022
High Yield Fortune Pvt Ltd
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects44 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
2 registrations of 4 moved past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Rivera Residence Phase 1Deregistered: Rivera Residence Phase 1 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Foresta Phase IIP52100046937 | Ravade | Certificate Signed | 31 Aug 2026 | 31 Aug 2026 | On date |
| Arkaya Phase IP52100054318 | Boribhadak | Certificate Signed | 31 Oct 2026 | 31 Oct 2028 | +24 mo |
| Rivera Residence Phase 1P52100079629 | Ravade | Certificate Signed | 31 Dec 2029 | 31 Dec 2029 | On date |
| Shere PalaceP52100080187 | Shere | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology