Gulabrao Suklal Dhangar

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shivam PrideP52100032049Kivale2021Certificate Signed31 Dec 202431 Dec 2025+12 months
Venkatesh PrideP52100034664Pimpri Chinchawad (M Corp.)2022Certificate Signed31 Dec 202431 Dec 2025+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shivam Pride+12 mo
  • Venkatesh Pride+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Shivam Pride (P52100032049).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology