0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 5 past their proposed date, not extended
+41 moMedian delayvs RERA proposed date · 5 extended
2Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ekta ParksvilleP99000000109Vasaivirar City (M Corp)2017Not reported30 Dec 202030 Dec 2023+36 months
Brooklyn ParkP99000000110Vasaivirar City (M Corp)2017Not reported31 Oct 201930 Sep 2023+47 months
Ekta ParksvilleP99000000116Vasaivirar City (M Corp)2017Not reported31 Dec 201927 Jul 2023+43 months
Brooklyn ParkP99000000134Vasaivirar City (M Corp)2017Not reported31 May 201930 Nov 2020+18 months
Brooklyn ParkP99000000148Vasaivirar City (M Corp)2017Not reported28 Feb 202027 Jul 2023+41 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ekta Parksville+36 mo
  • Brooklyn Park+47 mo
  • Ekta Parksville+43 mo
  • Brooklyn Park+18 mo
  • Brooklyn Park+41 mo

Track record notes

  • 0 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 47 months, for Brooklyn Park (P99000000110).
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology