Dipti Home Makers Pvt Ltd

Company or firm · 7 projects · 8 MahaRERA registrations

7Projects8 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date5 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Dipti Villa - KolhapurP53000003593Karvir2017Certificate Signed31 Jul 202331 Jul 2023On date
Dipti SkyCityP51700008856Ambarnath2017Certificate Signed31 Jul 202331 Jul 2023On date
Vishvaprem Co-operative Housing Society LimitedP51800009444Andheri2017Certificate Signed30 Jun 201830 Jun 2018On date
Dipti Sky City PHASE 2P51700016603Ambarnath2018Certificate Signed30 Jun 202330 Jun 2023On date
Surya Cooperative Housing Society LtdP51800018358Mumbai2018Certificate Signed30 Dec 202430 Dec 2024On date
Om Shivalaya CHS LtdP51800032469Andheri2022Certificate Signed31 Dec 202631 Dec 2026On date
Dipti SkyCityP51700048627Ambarnath2023Certificate Signed31 Dec 202630 Apr 2027+4 months
Om Sahil Co-operative Housing Society LimitedPR1180002600573Ismalia2026Certificate Signed31 Dec 203030 Apr 2031+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Dipti Villa - KolhapurOn date
  • Dipti SkyCityOn date
  • Vishvaprem Co-operative Housing Society LimitedOn date
  • Dipti Sky City PHASE 2On date
  • Surya Cooperative Housing Society LtdOn date
  • Om Shivalaya CHS LtdOn date
  • Dipti SkyCity+4 mo
  • Om Sahil Co-operative Housing Society Limited+4 mo

Track record notes

  • 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Dipti SkyCity (P51700048627).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology