Dilip Baburao Tupe

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
AstranaP52100055666Hadapsar2024Certificate Signed31 Jul 202831 Jul 2028On date
Freedom High StreetP52100055913Hadapsar2024Certificate Signed31 Dec 202631 Dec 2026On date
StellaP52100080288Hadapsar2025Certificate Signed31 Mar 202831 Jul 2028+4 months
AquilaP52100080347Hadapsar2025Certificate Signed30 Sep 202830 Jan 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • AstranaOn date
  • Freedom High StreetOn date
  • Stella+4 mo
  • Aquila+4 mo

Track record notes

  • Longest extension on record: 4 months, for Stella (P52100080288).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology