0Completedas reported on MahaRERA project pages
50%Kept RERA date5 of 10 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 15 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sector 22, TalojaP52000017425Pendhar2018Certificate Signed31 Mar 202130 Sep 2022+18 months
Sector 21 TalojaP52000017439Pendhar2018Certificate Signed31 Mar 202130 Sep 2022+18 months
Sector 37 Taloja (Renamed) /Sector 29 Taloja (Old)P52000017447Pendhar2018Certificate Signed31 Jan 202130 Apr 2022+15 months
Plot No -77 Sector -17 Kalamboli Bus DepotP52000028183Kalamboli2021Certificate Signed31 Aug 202831 Dec 2030+28 months
Plot No. 11 Sector-8 New Panvel West Bus TerminusP52000028195Khanda Colony2021Certificate Signed31 Jul 202731 Dec 2030+41 months
Plot No. 39 Sector-14 Kharghar Bus DepotP52000028196Kharghar2021Certificate Signed30 Jun 202530 Apr 2028+34 months
Plot No. 19 Sector-14 Kharghar Bus TerminusP52000028204Kharghar2021Certificate Signed31 Jul 202731 Dec 2030+41 months
Plot no -2 Sector -6 BamandongriP52000028209Bamandongri2021Certificate Signed30 Jun 202530 Jun 2025On date
Plot No. 1 Sector-28 TalojaP52000028219Taloje Panchnad2021Certificate Signed30 Jun 202530 Jun 2025On date
Plot No. 14 Sector-37 TalojaP52000028240Taloje Panchnad2021Certificate Signed30 Jun 202530 Oct 2025+4 months
Plot No -1 Sector - 28 Khandeshwar Railway StationP52000028246Kamothe2021Certificate Signed31 Dec 202731 Dec 2030+36 months
Plot No. 1 Sector-28 TalojaP52000028287Taloje Panchnad2021Certificate Signed30 Jun 202530 Jun 2025On date
Plot No -1A,Sector -19, Vashi Truck TerminalP51700030100Navi Mumbai (M Corp.)2021Certificate Signed31 Dec 202831 Dec 2030+24 months
Plot No -2,Sector-39,Mansarovar Railway StationP52000030419Kamothe2021Certificate Signed31 Dec 202631 Dec 2030+48 months
Plot No -7, Sector -1A, KhargharP52000032944Kharghar2022Certificate Signed31 Dec 202631 Dec 2027+12 months
Plot No -03, Sector -16A, Kharkopar RaiIway Station EastP52000033542Kharkopar2022Certificate Signed31 Dec 202630 Apr 2027+4 months
Plot No -2A, Sector -16 Kharkopar EastP52000033704Kharkopar2022Certificate Signed31 Dec 202531 Dec 2025On date
Plot No -2B, Sector -16 Kharkopar EastP52000033705Ulawe2022Certificate Signed31 Dec 202531 Dec 2025On date
Plot No. 1 Sector-28 TalojaP52000034514Taloje Panchnad2022Certificate Signed31 Dec 202631 Dec 2026On date
Plot No. 1 Sector-28 TalojaP52000045446Taloje Panchnad2022Certificate Signed31 Dec 202731 Dec 2027On date
Plot No 1 Sec-8A, Kharkopar WestP52000079747Kharkopar2025Certificate Signed1 May 20271 Sep 2027+4 months
Plot-03, Sector-16A, Kharkopar EastP52000079802Panvel2025Certificate Signed31 Dec 202830 Apr 2029+4 months
Show all 22 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sector 22, Taloja+18 mo
  • Sector 21 Taloja+18 mo
  • Sector 37 Taloja (Renamed) /Sector 29 Taloja (Old)+15 mo
  • Plot No -77 Sector -17 Kalamboli Bus Depot+28 mo
  • Plot No. 11 Sector-8 New Panvel West Bus Terminus+41 mo
  • Plot No. 39 Sector-14 Kharghar Bus Depot+34 mo
  • Plot No. 19 Sector-14 Kharghar Bus Terminus+41 mo
  • Plot no -2 Sector -6 BamandongriOn date
  • Plot No. 1 Sector-28 TalojaOn date
  • Plot No. 14 Sector-37 Taloja+4 mo
Show all 22 registrations
  • Plot No -1 Sector - 28 Khandeshwar Railway Station+36 mo
  • Plot No. 1 Sector-28 TalojaOn date
  • Plot No -1A,Sector -19, Vashi Truck Terminal+24 mo
  • Plot No -2,Sector-39,Mansarovar Railway Station+48 mo
  • Plot No -7, Sector -1A, Kharghar+12 mo
  • Plot No -03, Sector -16A, Kharkopar RaiIway Station East+4 mo
  • Plot No -2A, Sector -16 Kharkopar EastOn date
  • Plot No -2B, Sector -16 Kharkopar EastOn date
  • Plot No. 1 Sector-28 TalojaOn date
  • Plot No. 1 Sector-28 TalojaOn date
  • Plot No 1 Sec-8A, Kharkopar West+4 mo
  • Plot-03, Sector-16A, Kharkopar East+4 mo

Track record notes

  • 5 of 10 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 48 months, for Plot No -2,Sector-39,Mansarovar Railway Station (P52000030419).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology