Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Chaitanya KohinoorP51800024570Borivali2020Not reported30 Jun 2023—On date
Chaitanya Anand - Lunkhod CHSLP51800029553Andheri2021Not reported31 May 202431 Aug 2024+3 months
Chaitanya NishigandhP51900034202Ward Gnorth2022Not reported31 Dec 2024—On date
Chaitanya ShreyasP51800035185Andheri2022Not reported31 Dec 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Chaitanya KohinoorOn date
  • Chaitanya Anand - Lunkhod CHSL+3 mo
  • Chaitanya NishigandhOn date
  • Chaitanya ShreyasOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 3 months, for Chaitanya Anand - Lunkhod CHSL (P51800029553).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology