Skip to content

Chaitanya Nishigandh

Certificate Signed

Ward Gnorth, Maharashtra 400016 |Promoter: Chaitanya Developers

Residential / Group HousingRERAP51900034202
25 Mar 2022Registered with MahaRERA
31 Dec 2024Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Address
FP NO 101 A, Bal Govind Das Marg, Mahim WestPIN 400016
Designated bank account
76
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2024

The latest completion date on record passed 1 year and 10 months ago.

Registered
25 Mar 2022
Promised
31 Dec 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5190003420225 Mar 202231 Dec 202431 Dec 2024Chaitanya DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Chaitanya Nishigandh14—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

1 document held by Deedo, 72 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 17 Mar 2022Source

Legal

  • Legal Title reportTitle Certificate.pdf · uploaded 17 Mar 2022Source
  • Declaration Form BAffidavit cum declaration.pdf · uploaded 17 Mar 2022Source
  • Declaration Form BDeclaration about full CC.pdf · uploaded 20 Apr 2023Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 17 Mar 2022Source
  • 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 17 Mar 2022Source
  • 1 Details of encumbrancesNo encumbrances certificate.pdf · uploaded 17 Mar 2022Source
Show all 73 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)IOD Plan 1.pdf · uploaded 17 Mar 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentIOD Plan 1.pdf · uploaded 17 Mar 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentIOD Plan 2.pdf · uploaded 17 Mar 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentIOD Plan 3.pdf · uploaded 17 Mar 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentIOD Plan 4.pdf · uploaded 17 Mar 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentIOD Plan 5.pdf · uploaded 17 Mar 2022Source
  • 6 Building Plan Approval / NA Order for plotted development_IOD_signed.pdf · uploaded 17 Mar 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentPlinth CC.pdf · uploaded 17 Mar 2022Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 17 Mar 2022Source
  • 1 Declaration in FORM BAffidavit cum declaration.pdf · uploaded 17 Mar 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200232728744.pdf · uploaded 17 Mar 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 17 Mar 2022Source
  • 1 Proforma of Allotment letterDraft ALLOTMENT LETTER.pdf · uploaded 17 Mar 2022Source
  • 2 Proforma of Allotment letterDraft Sale Agreement.pdf · uploaded 17 Mar 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentFull CC 2 sept 22.pdf · uploaded 17 Apr 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jan 22 to March 22.pdf · uploaded 17 Apr 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 April to June 22.pdf · uploaded 17 Apr 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 July to Sept 22.pdf · uploaded 17 Apr 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Jan 22 to March 22.pdf · uploaded 17 Apr 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 April 22 to Jun 22.pdf · uploaded 17 Apr 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 2 July to Sept 22.pdf · uploaded 17 Apr 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Oct 22 to Dec 22.pdf · uploaded 17 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 April 21 to March 22.pdf · uploaded 17 Apr 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A Declaration of Bank Account.pdf · uploaded 18 Apr 2023Source
  • 2 Declaration about Commencement CertificateDeclaration about full CC.pdf · uploaded 20 Apr 2023Source
  • 2 Declaration in FORM BDeclaration about full CC.pdf · uploaded 20 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 April 21 to March 22.pdf · uploaded 20 Apr 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold and unsold of flats.pdf · uploaded 25 Apr 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Jan 22 to Mar 22.pdf · uploaded 9 May 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Apr 22 to Jun 22.pdf · uploaded 9 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Jul 22 to Sep 22.pdf · uploaded 9 May 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Oct 22 to Dec 22.pdf · uploaded 9 May 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Nishi March 23.pdf · uploaded 9 May 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Oct 22 to Dec 22.pdf · uploaded 9 May 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Nishi March 23.pdf · uploaded 9 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Nishi March 23.pdf · uploaded 9 May 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Nishi March 23.pdf · uploaded 9 May 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Nishi March 23.pdf · uploaded 9 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A Certificate for Quality Assurance 22-23 Nishi.pdf · uploaded 16 Aug 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 16 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Auditor Certificate 2023.pdf · uploaded 16 Aug 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Chaitanya Nishigandh Form 1.pdf · uploaded 29 Oct 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Chaitanya Nishigandh Form 2.pdf · uploaded 29 Oct 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Chaitanya Nishigandh Form 3.pdf · uploaded 29 Oct 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Nishigandh.pdf · uploaded 1 Mar 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 NIshigandh.pdf · uploaded 1 Mar 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure Sold Unsold Nishigandh.pdf · uploaded 1 Mar 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Nishigandh.pdf · uploaded 1 Mar 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Nishigandh.pdf · uploaded 10 Jun 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Nishigandh.pdf · uploaded 10 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Nishigandh.pdf · uploaded 10 Jun 2024Source
  • 3 Disclosure of sold/ booked inventoryDisclosure of Sold and Unsold.pdf · uploaded 10 Jun 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Nishigandh.pdf · uploaded 10 Jun 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Nishigandh.pdf · uploaded 10 Jun 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Nishigandh.pdf · uploaded 27 Nov 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentNishigandh OC.pdf · uploaded 27 Nov 2024Source

Technical

  • DocumentIOD Plan 1.pdf · uploaded 17 Mar 2022Source
  • DocumentIOD Plan 1.pdf · uploaded 17 Mar 2022Source
  • DocumentIOD Plan 2.pdf · uploaded 17 Mar 2022Source
  • DocumentIOD Plan 3.pdf · uploaded 17 Mar 2022Source
  • DocumentIOD Plan 4.pdf · uploaded 17 Mar 2022Source
  • DocumentIOD Plan 5.pdf · uploaded 17 Mar 2022Source
  • Document_IOD_signed.pdf · uploaded 17 Mar 2022Source

Technical (Architect)

  • DocumentForm 1 Nishigandh.pdf · uploaded 10 Jun 2024Source

Technical (Engineer)

  • DocumentForm 2 Nishigandh.pdf · uploaded 10 Jun 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

Survey, CTS, gat or plot numbers

FP NO 101 A

Boundaries

North
Cts No 101 B
South
Dp Road
East
Cts No 98
West
Cts No 102

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRasik P Hingoo Associates—
Chartered accountantHaresh Dhaduk & Associates—
EngineerChakor R Raul—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology