Company or firm · first RERA registration 2017
Bharat Mahan Developers & Builders
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 72 mo — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay72 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Orchid MetropolisP51800005064 | Kurla | Certificate Signed | 31 Jul 2018 | 31 Jul 2024 | +72 mo |
| Ruparel CrestP51800052788 | Kurla | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology