Bhaishree Ventures

Company or firm · 3 projects · 3 MahaRERA registrations · 2 reported completed

3Projects3 RERA registrations
2Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
VrundavanP51500003771Kubhephal2017Completed31 Dec 2018—On date
Geetaban ResidencyP51500016327Sawangi2018Completed30 Dec 2021—On date
SwapnabanP51500016418Kubhephal2018Certificate Signed30 Dec 202230 Dec 2022On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • VrundavanOn date
  • Geetaban ResidencyOn date
  • SwapnabanOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology