Belvalkar Realtors LLP

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Parichay Co-Op Housing Society LtdP52100055315Peth2024Certificate Signed31 Mar 202731 Jul 2027+4 months
YashodhanPR1260002600508Erandwana North2026Not reported30 Oct 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Parichay Co-Op Housing Society Ltd+4 mo
  • YashodhanOn date

Track record notes

  • Longest extension on record: 4 months, for Parichay Co-Op Housing Society Ltd (P52100055315).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology