Ankit Construction

Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed

3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
27Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
K-Square ApartmentsP50500003259Nagpur (M Corp.)2017Completed31 Mar 2019—On date
K-Square-BalewadiP52100003794Haveli2017Certificate Signed30 May 202230 May 2023+12 months
K-Square NeriumP50500030653Nagpur (M Corp.)2021Certificate Signed31 Dec 202531 Dec 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • K-Square ApartmentsOn date
  • K-Square-Balewadi+12 mo
  • K-Square NeriumOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for K-Square-Balewadi (P52100003794).

Regulatory cases across projects

Show all 27 cases
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology