Anandtara Infrastructure
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Anandtara Whitefield Residences Phase - IP52100007529 | Mundhawa | 2017 | Certificate Signed | 30 Jun 2019 | 29 Dec 2020 | +18 months |
| Anandtara Whitefield Residencies Phase-IIP52100018257 | Mundhawa | 2018 | Certificate Signed | 28 Feb 2021 | 28 Aug 2022 | +18 months |
| Anandtara Iris Residences Phase IP52100054845 | Keshavnagar Mundwa | 2024 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Anandtara Iris Residences Phase IIP52100055274 | Keshavnagar Mundwa | 2024 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Anandtara Iris Residences Phase IIIPR1260002600494 | Mundhawa | 2026 | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Anandtara Whitefield Residences Phase - I (P52100007529).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology