Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Anandtara Whitefield Residences Phase - IP52100007529Mundhawa2017Certificate Signed30 Jun 201929 Dec 2020+18 months
Anandtara Whitefield Residencies Phase-IIP52100018257Mundhawa2018Certificate Signed28 Feb 202128 Aug 2022+18 months
Anandtara Iris Residences Phase IP52100054845Keshavnagar Mundwa2024Certificate Signed31 Dec 202630 Apr 2027+4 months
Anandtara Iris Residences Phase IIP52100055274Keshavnagar Mundwa2024Certificate Signed31 Dec 202631 Dec 2026On date
Anandtara Iris Residences Phase IIIPR1260002600494Mundhawa2026Certificate Signed30 Jun 202930 Oct 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anandtara Whitefield Residences Phase - I+18 mo
  • Anandtara Whitefield Residencies Phase-II+18 mo
  • Anandtara Iris Residences Phase I+4 mo
  • Anandtara Iris Residences Phase IIOn date
  • Anandtara Iris Residences Phase III+4 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Anandtara Whitefield Residences Phase - I (P52100007529).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology