Alag Property Constructions Pvt. Ltd

Company or firm · 4 projects · 4 MahaRERA registrations

Also appears as ALAG PROPERTY CONSTRUCTIONS PVT. LTD.

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 3 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Alag MarinaP51800003162Kurla2017Not reported31 Dec 2026—On date
Alag BellaP51800006661Kurla2017Not reported31 Dec 201730 Jun 2018+6 months
Alag StellaP51800018925Kurla2018Not reported30 Jun 202130 Dec 2022+18 months
Alag CapitalP51800020773Kurla2019Active30 Jun 202431 Dec 2026+30 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Alag MarinaOn date
  • Alag Bella+6 mo
  • Alag Stella+18 mo
  • Alag Capital+30 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Alag Capital (P51800020773).
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology