Individual promoter · first RERA registration 2020
Ajay Ananta Patil
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects44 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 4 moved past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Janai ComplexP52000023813 | Vadghar (Ct) | Certificate Signed | 8 Nov 2023 | 8 Nov 2023 | On date |
| Siddhivinayak SparshP52000052949 | Dapoli | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Ambika NiwasP52000053693 | Karanjade | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Siddhivinayak HorizonPM1270002501639 | Pushpak Nagar | Certificate Signed | 31 Mar 2030 | 31 Jul 2030 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology