A.M.Patel Infra Pvt Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+3 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
180 and 51 GreensP51500004770Aurangabad (M Corp.)2017Not reported31 Jul 202331 Jan 2024+6 months
36 GreensP51500050638Golwadi2023Not reported30 Nov 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • 180 and 51 Greens+6 mo
  • 36 GreensOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 6 months, for 180 and 51 Greens (P51500004770).