A.M.Patel Infra Pvt Ltd
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+3 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| 180 and 51 GreensP51500004770 | Aurangabad (M Corp.) | 2017 | Not reported | 31 Jul 2023 | 31 Jan 2024 | +6 months |
| 36 GreensP51500050638 | Golwadi | 2023 | Not reported | 30 Nov 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 6 months, for 180 and 51 Greens (P51500004770).
Regulatory cases across projects
- Quarterly progress report not filedQuarterly progress report not filed: 36 Greens · 36 Greens · P51500050638
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology