Projects compared side by side
Amravati (M Corp.) · Amravati
Registration
RERA numbers
PromoterNitin Bhatkar
Status on MahaRERAActive
Registered on31 May 2024
Delivery
Promised completion31 Dec 2028
Revised completion—
Delay vs RERA dateNonepromised date not yet reached
Extension certificates0
Size
Project land area1,568 sq m
Buildings on record2
Units—
Units booked—
Regulatory
MahaRERA cases0
Documents on file33
Last checked on MahaRERA15 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology