M/S. Empower Infrastructure · Wadi
Delivery
Status1 yr 9 mo late
Promised → actualDec 2024 → still open
Extension certificates0
Size & sales
Units booked3 / 12 · 25%
Buildings · land1 · —
Registration
RERA numbers
Status on MahaRERACertificate Signed
Registered on13 Jan 2023
Regulatory
MahaRERA cases1Deregistered
Documents on file90
Last checked on MahaRERA13 Oct 2026

✓ marks the best value only where “best” is unambiguous. Prices are not ranked; medians need at least 3 registered deeds.

Add a second

Add at least one more project to see which values are better.

Data through13 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pages; registered documents (Index II) for pricesDelay counts months from the completion date promised at registration.Methodology