Gotal Panjari · Nagpur
Registration
RERA numbers
PromoterAlliance Infrastructure
Status on MahaRERALapsed
Registered on8 Jul 2019
Delivery
Promised completion28 Feb 2025
Revised completion—
Delay vs RERA date+1 year and 7 monthslatest date on record has passed
Extension certificates0
Size
Project land area5,233 sq m
Buildings on record1
Units—
Units booked—
Regulatory
MahaRERA cases0
Documents on file11
Last checked on MahaRERA9 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.