Skip to content
Deedo home
Menu

Compare

Compare projects side by side

Pick up to four MahaRERA-registered projects to see their delivery, registered prices, sales and regulatory record next to each other.

Projects compared side by side
Surendra Mody And Others · Mumbai City
Delivery
Status8 yrs 9 mo late
Promised → actualDec 2017 → still open
Extension certificates0
Size & sales
Units booked14 / 22 · 64%
Buildings · land1 · —
Registration
RERA numbers
Status on MahaRERACertificate Signed
Registered on31 Aug 2017
Regulatory
MahaRERA cases0
Documents on file1
Last checked on MahaRERA13 Oct 2026

✓ marks the best value only where “best” is unambiguous. Prices are not ranked; medians need at least 3 registered deeds.

Add a second

Add at least one more project to see which values are better.

Data through13 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pages; registered documents (Index II) for pricesDelay counts months from the completion date promised at registration.Methodology