Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Gangapur Jahagir · Aurangabad
Registration
RERA numbers
PromoterVansh Infrastructure
Status on MahaRERALapsed
Registered on7 Feb 2018
Delivery
Promised completion19 Feb 2022
Revised completion—
Delay vs RERA date+4 years and 7 monthslatest date on record has passed
Extension certificates0
Size
Project land area8,890 sq m
Buildings on record7
Units172
Units booked—
Regulatory
MahaRERA cases0
Documents on file19
Last checked on MahaRERA10 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through10 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology