Compare projects side by side
Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.
| Nashik (M Corp.) · Nashik | |
|---|---|
| Registration | |
| RERA numbers | |
| Promoter | Sanklecha Construction Private Limited |
| Status on MahaRERA | Completed |
| Registered on | 17 Aug 2017 |
| Delivery | |
| Promised completion | 30 Jun 2018 |
| Revised completion | 31 Oct 2022 |
| Delay vs RERA date | +4 years and 4 monthsrevised completion date |
| Extension certificates | 1 |
| Size | |
| Project land area | 2,153 sq m |
| Buildings on record | 2 |
| Units | 24 |
| Units booked | — |
| Regulatory | |
| MahaRERA cases | 1Suo motu order |
| Documents on file | 26 |
| Last checked on MahaRERA | 11 Oct 2026 |
Add a project
Search by project name, RERA number or building.
Add at least one more project to see which values are better.
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology