Krushna Sneha Nagari

Completed

Brahmapuri (M Cl), Chandrapur 441206 |Promoter: Gaurav Ashok Bhaiyya and Ashok K. Bhaiyya

22 Feb 2022Registered with MahaRERA
31 Mar 2023Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Completed
Land area for this project
9,163 sq m (98,632 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
1,480 sq m (15,934 sq ft)
Address
305, BramhapuriPIN 441206
Designated bank account
Union Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Krushna Sneha Nagari is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2023

The latest completion date on record passed 3 years and 7 months ago.

Registered
22 Feb 2022
Promised
31 Mar 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5090003354122 Feb 202231 Mar 2023—Gaurav Ashok Bhaiyya and Ashok K. BhaiyyaProject page

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsCement Road100%
  • Water SupplyBorewell100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Cement Nali100%
  • Storm Water DrainsAs per Sanction100%
  • Landscaping & Tree PlantingTree plantation100%
  • Street LightingStreet Light100%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAs per Sanction100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAs Per Sanction100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

33 documents held by Deedo, 43 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title report4 SEARCH REPORT.pdf · uploaded 5 Feb 2022View
  • Details of encumbrances5 encumbrance Certificate Partnership.pdf · uploaded 5 Feb 2022View
  • Copy of Layout Approval (in case of layout)10 LAYOUT MAP.pdf · uploaded 5 Feb 2022View
  • Building Plan Approval / NA Order for plotted development7 NA CORRECTED ORDER (नगर परिषद).pdf · uploaded 5 Feb 2022View
  • Commencement Certificates / NA Order for plotted development7 NA CORRECTED ORDER (नगर परिषद).pdf · uploaded 5 Feb 2022View
  • Declaration about Commencement Certificate11 circular 32_ Declaration about commencement certificate.pdf · uploaded 5 Feb 2022View
  • Declaration in FORM B6 FORM-B-AFFIDAVIT.pdf · uploaded 5 Feb 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Form 1.pdf · uploaded 5 Feb 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Form 2.pdf · uploaded 5 Feb 2022View
  • Disclosure of sold/ booked inventory12 Annexure - 29.pdf · uploaded 5 Feb 2022View
  • Proforma of Allotment letter9 kararnama.pdf · uploaded 5 Feb 2022View
  • Proforma of Allotment letter8 Allotment Letter.pdf · uploaded 5 Feb 2022View
  • OtherKrushna Sneha Nagari Cert.pdf · uploaded 5 Feb 2022View
  • CERSAI details13 CERSAI_Search_Report_200229769212_For_Asset_Based_Search_08_02_2022_13_57_44_147.pdf · uploaded 8 Feb 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31-03-2022.pdf · uploaded 14 Feb 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 30-06-2022.pdf · uploaded 14 Feb 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 30-09-2022.pdf · uploaded 14 Feb 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 15-11-2022.pdf · uploaded 14 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 31-3-22.pdf · uploaded 14 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 15-11-2022.pdf · uploaded 14 Feb 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)1_Form 2A 31-3-22.pdf · uploaded 14 Feb 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)4_fORM 2 A 15-11-2022.pdf · uploaded 14 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)1_Form 2 31-03-2022.pdf · uploaded 16 Feb 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2_Form 2 30-06-2022.pdf · uploaded 16 Feb 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)3_Form 2 30-09-2022.pdf · uploaded 16 Feb 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)4_Form 2 15-11-2022.pdf · uploaded 16 Feb 2023View
  • Disclosure of sold/ booked inventory1_Annexure 29 30-03-2022.pdf · uploaded 16 Feb 2023View
  • Disclosure of sold/ booked inventory2_Annexure 29 30-06-2022.pdf · uploaded 16 Feb 2023View
  • Disclosure of sold/ booked inventory3_Annexure 29 30- 09-2022.pdf · uploaded 16 Feb 2023View
  • Disclosure of sold/ booked inventory4_Annexure 29 15-11-2022.pdf · uploaded 16 Feb 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 3 May 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development4_Form 4.pdf · uploaded 3 May 2023View
  • Architect’s Certificate on Completion of Project (Form 4)4_Form 4.pdf · uploaded 3 May 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)2_Form 2 30-06-2022.pdf · uploaded 22 May 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)3_Form 2 30-09-2022.pdf · uploaded 22 May 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)4_Form 2 15-11-2022.pdf · uploaded 22 May 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 15-11-2022.pdf · uploaded 16 Sep 2023View

Promoter documents

  • Legal Title report4 SEARCH REPORT.pdf · uploaded 5 Feb 2022View
  • Declaration Form B6 FORM-B-AFFIDAVIT.pdf · uploaded 5 Feb 2022View

Technical documents

  • Layout Approval10 LAYOUT MAP.pdfView
  • NA Order for Plotted Development7 NA CORRECTED ORDER (नगर परिषद).pdfView

Other legal documents

  • OtherKrushna Sneha Nagari Cert.pdfView

Proforma allotment letter

  • Proforma allotment letter9 kararnama.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Brahmapuri (M Cl), Brahmapuri taluka

Survey, CTS, gat or plot numbers

305

As published on MahaRERA's project page

305

Boundaries

North
Survey No 376
South
railway land
East
Survey No 306
West
Survey no 377 and 379

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSachin Kadhikhaye—
Chartered accountantCa Abhinav Welekar—
EngineerSachin kladhikhaye—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology