Dream Home

Completed

Yelgaon, Buldana 443001 |Promoter: Sukhkarta Builders And Developers

Residential / Group HousingRERAP50000013451
7 Oct 2017Registered with MahaRERA
31 Aug 2018Promised completion
14Buildings
14Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
14
Unit types
Row house14 units in all
Land area for this project
1,174 sq m (12,631 sq ft)
Permissible built-up area
1,119 sq m (12,047 sq ft)
Sanctioned built-up area
1,119 sq m (12,047 sq ft)
Address
Gut No 434/Plot No 32a, 32b, 34a, 34b, 35a, 35b, 36a, 36b, 41a, 41b, 42a, 42b, 43a, 43bPIN 443001
Designated bank account
Axis Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.47881, 76.21001
Dream Home is at latitude 20.47881, longitude 76.21001.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Aug 2018

The latest completion date on record passed 8 years and 2 months ago.

Registered
7 Oct 2017
Promised
31 Aug 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P500000134517 Oct 201731 Aug 2018—Sukhkarta Builders And DevelopersProject page

14 buildings

Buildings and wings named in the registration

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

14 units registered

Row house · 14 units
BuildingTypeCarpet areaUnits
Row House No 1Row house63.23 sq m · 681 sq ft1
Row House No 10Row house71.96 sq m · 775 sq ft1
Row House No 11Row house71.96 sq m · 775 sq ft1
Row House No 12Row house71.96 sq m · 775 sq ft1
Row House No 13Row house71.96 sq m · 775 sq ft1
Row House No 14Row house71.96 sq m · 775 sq ft1
Row House No 2Row house62.6 sq m · 674 sq ft1
Row House No 3Row house60.6 sq m · 652 sq ft1
Row House No 4Row house60.6 sq m · 652 sq ft1
Row House No 5Row house60.6 sq m · 652 sq ft1
Row House No 6Row house60.6 sq m · 652 sq ft1
Row House No 7Row house60.6 sq m · 652 sq ft1
Row House No 8Row house60.77 sq m · 654 sq ft1
Row House No 9Row house68.27 sq m · 735 sq ft1

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Row House No 1Closed/Covered00000
Row House No 1Open Space00001
Row House No 10Closed/Covered00000
Row House No 10Open Space00001
Row House No 11Closed/Covered00000
Row House No 11Open Space00001
Row House No 12Closed/Covered00000
Row House No 12Open Space00001
Row House No 13Closed/Covered00000
Row House No 13Open Space00001
Row House No 14Closed/Covered00000
Row House No 14Open Space00001
Row House No 2Closed/Covered00000
Row House No 2Open Space00001
Row House No 3Closed/Covered00000
Row House No 3Open Space00001
Row House No 4Closed/Covered00000
Row House No 4Open Space00001
Row House No 5Closed/Covered00000
Row House No 5Open Space00001
Row House No 6Closed/Covered00000
Row House No 6Open Space00001
Row House No 7Closed/Covered00000
Row House No 7Open Space00001
Row House No 8Closed/Covered00000
Row House No 8Open Space00001
Row House No 9Closed/Covered00000
Row House No 9Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Row House No 1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 10

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 11

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 12

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 13

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 14

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 3

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 4

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 5

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 6

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 7

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 8

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 9

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsWBM ROADS100%
  • Water SupplyBORE WELL100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingPER ROW HOUSE100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

19 documents held by Deedo, 28 filings listed on MahaRERA's project page

Titles

Encumbrance

Commencement certificates

Form bs

Registration certificate

Form 4s

Form 5

Others

Layout plans

Building plan

Allotment letter

Document library

  • Copy of the legal title reportlegal title report 1.pdf · uploaded 20 Sep 2017View
  • Copy of the legal title reportlegal title report 2.pdf · uploaded 20 Sep 2017View
  • Details of encumbrancesdetails of encumbrances.pdf · uploaded 20 Sep 2017View
  • Copy of Layout Approval (in case of layout)NA ORDER.pdf · uploaded 20 Sep 2017View
  • Copy of Layout Approval (in case of layout)lay out copy 1.pdf · uploaded 20 Sep 2017View
  • Declaration in FORM Bform b.pdf · uploaded 20 Sep 2017View
  • Proforma of Allotment letterproforma of agreement for sale.pdf · uploaded 20 Sep 2017View
  • Commencement Certificates / NA Order for plotted developmentcommecement certificate 1.pdf · uploaded 20 Sep 2017View
  • Commencement Certificates / NA Order for plotted developmentcommencement ceriticate 2.pdf · uploaded 20 Sep 2017View
  • Building Plan Approval (IOD)bldg plan approve.pdf · uploaded 20 Sep 2017View
  • Declaration in FORM BPDF.pdf · uploaded 14 Dec 2017View
  • Certificates of Architect (Form 4)4.pdf · uploaded 3 Oct 2018View
  • Certificates of Architect (Form 4)gp.pdf · uploaded 3 Oct 2018View
  • Certificates of Architect (Form 4)form 4.pdf · uploaded 3 Oct 2018View
  • Certificates of Architect (Form 4)form 4s.pdf · uploaded 3 Oct 2018View
  • Otherphoto pdf.pdf · uploaded 3 Oct 2018View
  • Otherdream home compelted site photos.pdf · uploaded 3 Oct 2018View
  • Certificates of CA (Form 5)SUKHKARTA BUIDLERS - FORM 5 - RERA (1).pdf · uploaded 30 Dec 2018View

Promoter documents

  • Legal Title reportlegal title report 1.pdf · uploaded 20 Sep 2017View
  • Legal Title reportlegal title report 2.pdf · uploaded 20 Sep 2017View
  • Declaration Form Bform b.pdf · uploaded 20 Sep 2017View
  • Declaration Form BPDF.pdf · uploaded 14 Dec 2017View

Technical documents

  • Layout ApprovalNA ORDER.pdfView
  • Layout Approvallay out copy 1.pdfView
  • Building Plan Approvalbldg plan approve.pdfView

Other legal documents

  • Otherphoto pdf.pdfView
  • Otherdream home compelted site photos.pdfView

Proforma allotment letter

  • Proforma allotment letterproforma of agreement for sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Yelgaon, Buldana taluka

Survey, CTS, gat or plot numbers

32B34A34B35A35B36A36B41A41B42A42B43A43BGUT NO 434/PLOT NO 32A

As published on MahaRERA's project page

GUT NO 434/PLOT NO 32A,32B,34A,34B,35A,35B,36A,36B,41A,41B,42A,42B,43A,43B

Boundaries

North
Plot No 37 And Plot No 40
South
6 Meter Road
East
9 Meter Road
West
9 Meter Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAniket A Shewale—
ArchitectPrafulla P Narkhede—
OtherMohsin Kha Shabbir Kha—

Source: MahaRERA project page. Contact details are not shown.