BLD_006939Completed7 floors

Dhiraj Rambhau Lingade · The Vista Apartment

Buldana (Mcl) · RERA P50000049844

7Sanctioned habitable floorsregistration certificate
31 Mar 2024Revised completionpromised 30 Nov 2023

Floors

7 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P50000049844 · registered 6 Mar 2023
Promised completion
30 Nov 2023
Revised completion
31 Mar 2024
Sanctioned habitable floors
7

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK57.3 m² (617 sq.ft)5not published
2BHK60.5 m² (651 sq.ft)1not published
2BHK62.9 m² (677 sq.ft)22not published
2BHK63.1 m² (679 sq.ft)2not published
3BHK77.8 m² (837 sq.ft)5not published
3BHK82.3 m² (885 sq.ft)4not published
3BHK88.3 m² (950 sq.ft)1not published
Total40

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered00033
Open Space0000

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology