Orchid Towers
Certificate SignedSatara (Ct), Aurangabad 431005 |Promoter: Savali Constructions
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 2BHK15 units in all
- Address
- Plot No.4, Gut No.90/2, Amdar Road, Padmawati Nagari, Near Sangram NagarPIN 431005
- Designated bank account
- 85
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2023
The latest completion date on record passed 2 years and 10 months ago.
- Registered
- 3 Feb 2022
- Promised
- 30 Dec 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51500033091 | 3 Feb 2022 | 30 Dec 2023 | 30 Dec 2023 | Savali Constructions | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Orchid Towers | 6 | 15 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
15 of 15 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 60.13 sq m · 647 sq ft | 5 | 5 |
| 2BHK | 68.56 sq m · 738 sq ft | 10 | 10 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 37 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card.pdf · uploaded 11 Dec 2021Source
Legal
Migrated
- 1 PAN CardPan Card.pdf · uploaded 11 Dec 2021Source
- 1 Details of encumbrancesNo Encumbrances.pdf · uploaded 11 Dec 2021Source
- 1 Copy of Layout Approval (in case of layout)Approval Plan.pdf · uploaded 11 Dec 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentApproval Plan.pdf · uploaded 11 Dec 2021Source
Show all 38 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCommcement Certificate.pdf · uploaded 11 Dec 2021Source
- 1 Declaration in FORM BForm-B.pdf · uploaded 11 Dec 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Form No3.pdf · uploaded 11 Dec 2021Source
- 1 Proforma of Allotment letterBooking Letter and Agreement To Sale Draft.pdf · uploaded 11 Dec 2021Source
- 1 Declaration about Commencement CertificateFormat - D Declaration About Commecement Certifcate.pdf · uploaded 15 Dec 2021Source
- 1 CERSAI details15122021 CERSAI Search Report.pdf · uploaded 15 Dec 2021Source
- 1 Copy of the legal title report25112021 Title Search Report.pdf · uploaded 24 Dec 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)28012022 Architect Certificate Form No1.pdf · uploaded 28 Jan 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)28012022 Engineer Certificate Form No2.pdf · uploaded 28 Jan 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)24052022 Architect Certificate Form No 1 Up To March 2022.pdf · uploaded 24 May 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)24052022 Engineer Certificate Form No 2 Up To March 2022.pdf · uploaded 24 May 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)13012023 CA Form No5 202122.pdf · uploaded 14 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM2A QUALITY ASSURANCE CERTIFICATE UP TO MARCH 2022.pdf · uploaded 27 Feb 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)28062023 Architect Certificate Form No1UpToMarch2023.pdf · uploaded 30 Jun 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)24062023 Engineer Certificate Form No2UpToMarch2023.pdf · uploaded 30 Jun 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM2A QUALITY ASSURANCE CERTIFICATE UP TO MARCH 2023.pdf · uploaded 6 Jul 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)17072023 Form1 Architect Certificate Up To April To June 2023.pdf · uploaded 18 Jul 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)17072023 Form2 Engineer Certificate Up To April To June 2023.pdf · uploaded 18 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)31082023 CA Form No5 202223.pdf · uploaded 11 Sep 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Achitect Certificate.pdf · uploaded 18 Oct 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 18 Oct 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development13012024 Occupancy Certificate.pdf · uploaded 13 Jan 2024Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development13012024 Completion Plan.pdf · uploaded 13 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)13012024 Form1 Architect Certificate Up To October To December 2023.pdf · uploaded 18 Jan 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)13012024 FORM4 Architect Certificate for Completion.pdf · uploaded 18 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form5.pdf · uploaded 14 Aug 2024Source
Technical
Technical (Architect)
- Document13012024 Form1 Architect Certificate Up To October To December 2023.pdf · uploaded 18 Jan 2024Source
Technical (Engineer)
- DocumentForm 2 Engineer Certificate.pdf · uploaded 18 Oct 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Satara (CT), Aurangabad taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 3
- South
- Plot No 5
- East
- Remaining Land From Gut N0 90
- West
- 12 Mtr Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Kapil Gujarathi | — |
| Chartered accountant | Eknath M Bhalerao | — |
| Chartered accountant | Vaibhav Vijay Dande | — |
| Engineer | Pramod K Mutha | — |
Source: MahaRERA project page. Contact details are not shown.