Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Completed
- Buildings
- 1
- Unit types
- 2BHK16 units in all
- Land area for this project
- 728 sq m (7,833 sq ft)
- Permissible built-up area
- 1,981 sq m (21,318 sq ft)
- Sanctioned built-up area
- 1,261 sq m (13,568 sq ft)
- Address
- Plot No 12 And 13 Gut No 162 Satara Aurangabad, Satara Parisar, Satata ParisarPIN 431002
- Designated bank account
- State Bank Of India
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Mar 2023
The latest completion date on record passed 3 years and 7 months ago.
- Registered
- 12 Nov 2021
- Promised
- 31 Mar 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51500031801 | 12 Nov 2021 | 31 Mar 2023 | — | Arihant Enterprises | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Ajinkya Apartment | 5 | 16 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
16 units registered
| Type | Carpet area | Units |
|---|---|---|
| 2BHK | 58.45 sq m · 629 sq ft | 4 |
| 2BHK | 58.69 sq m · 632 sq ft | 8 |
| 2BHK | 59.19 sq m · 637 sq ft | 4 |
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 1 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Ajinkya Apartment
Show all 11 activitiesShow fewer activities
Common areas and amenities
Show all 15 activitiesShow fewer activities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
16 documents held by Deedo, 21 filings listed on MahaRERA's project page
Commencement certificate (2)
Show all 37 documentsShow fewer documents
Document library
- Copy of the legal title reportSearch Report.pdf · uploaded 29 Oct 2021View
- Details of encumbrancesAjinkya Apartment Lettarhead.pdf · uploaded 29 Oct 2021View
- Commencement Certificates / NA Order for plotted developmentAjinkya Apartment Commencement Certificate.pdf · uploaded 29 Oct 2021View
- Declaration about Commencement CertificateAjinkya Apartment Format -D.pdf · uploaded 29 Oct 2021View
- Declaration in FORM BAjinkya Apartment Form B.pdf · uploaded 29 Oct 2021View
- Proforma of Allotment letterProforma of Allotment Letter.pdf · uploaded 29 Oct 2021View
- Copy of Layout Approval (in case of layout)Plan Permission.pdf · uploaded 29 Oct 2021View
- Building Plan Approval / NA Order for plotted developmentPlan Permission.pdf · uploaded 29 Oct 2021View
- Proforma of Allotment letterProforma of the allotment letter and agreement for sale.pdf · uploaded 29 Oct 2021View
- Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Arihant Enterprises Form 5 Annual Report_compressed.pdf · uploaded 10 Feb 2023View
- Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2 A.pdf · uploaded 10 Feb 2023View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 10 Feb 2023View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC .pdf · uploaded 20 Mar 2023View
- Architect’s Certificate on Completion of Project (Form 4)Adobe Scan 20-Jul-2023 (4).pdf · uploaded 20 Jul 2023View
- Status of Formation of Legal Entity (Society/Co Op etc.)DOD_compressed.pdf · uploaded 20 Jul 2023View
- Status of ConveyanceDOD_compressed.pdf · uploaded 20 Jul 2023View
Promoter documents
Technical documents
Proforma allotment letter
- Proforma allotment letterProforma of the allotment letter and agreement for sale.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Satara (CT), Aurangabad taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
PLOT NO 12 AND 13 GUT NO 162 SATARA AURANGABAD
Boundaries
- North
- Part Gut No 161
- South
- Nala
- East
- 6 Mter Wide Road
- West
- Nala
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Arch Pramod Narale | — |
| Chartered accountant | S M P and Associates | — |
| Engineer | Pradeep Mote | — |
Source: MahaRERA project page. Contact details are not shown.