Nandgaon Peth, Amravati 444901 |Promoter: Steelarrow Commercial LLP

28 Jun 2024Registered with MahaRERA
31 Mar 2027Promised completion
5Buildings
57Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Active
Buildings
5
Unit types
Shop57 units in all
Land area for this project
9,559 sq m (1,02,895 sq ft)
Permissible built-up area
11,680 sq m (1,25,719 sq ft)
Sanctioned built-up area
11,680 sq m (1,25,719 sq ft)
Planning authority
TAHSILDAR AMRAVATI
Address
Plot No 795 S No76, 77, 459, 460/1, 460/1-C, 460/2, 460/3, 461/2, 458/1, 458/2, 464/1, 464/2, 464/3, 463/1/A/1, 461/1/A/2, 463/1/A/3, 463/1/C, 461/1 And 461/1/A Mouje Borgaon Dharmale And Nandgaonpeth Part 2 Prangane Nandgaon Peth, National Highway 6, Borgaon DharmalePIN 444901
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.99551, 77.79344
Govinda Arcade is at latitude 20.99551, longitude 77.79344.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2027

Registered
28 Jun 2024
Promised
31 Mar 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030007678728 Jun 202431 Mar 2027—Steelarrow Commercial LLPProject page

5 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A1321
A2311
A333
A434
A5318

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

57 units registered

Shop · 57 units
BuildingTypeCarpet areaUnits
A1Shop61.12 sq m · 658 sq ft6
A1Shop120.75 sq m · 1,300 sq ft5
A1Shop124.11 sq m · 1,336 sq ft6
A1Shop124.29 sq m · 1,338 sq ft1
A1Shop125.08 sq m · 1,346 sq ft1
A1Shop125.22 sq m · 1,348 sq ft1
A1Shop280.16 sq m · 3,016 sq ft1
A2Shop86.36 sq m · 930 sq ft3
A2Shop89.58 sq m · 964 sq ft4
A2Shop89.66 sq m · 965 sq ft2
A2Shop129.14 sq m · 1,390 sq ft1
A2Shop137.03 sq m · 1,475 sq ft1
A3Shop85.56 sq m · 921 sq ft1
A3Shop103.63 sq m · 1,115 sq ft2
A4Shop86.09 sq m · 927 sq ft2
A4Shop86.62 sq m · 932 sq ft1
A4Shop143.87 sq m · 1,549 sq ft1
A5Shop82 sq m · 883 sq ft6
A5Shop99.06 sq m · 1,066 sq ft1
A5Shop124.42 sq m · 1,339 sq ft4
A5Shop124.53 sq m · 1,340 sq ft5
A5Shop126.78 sq m · 1,365 sq ft1
A5Shop176.4 sq m · 1,899 sq ft1

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
A1Closed/Covered00000
A1Open Space0000100
A2Closed/Covered00000
A2Open Space000068
A3Closed/Covered00000
A3Open Space000037
A4Closed/Covered00000
A4Open Space000052
A5Closed/Covered00000
A5Open Space0000100

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

A1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor35%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A3

  • Excavation100%
  • Basement (if any)90%
  • Podiums (if any)0%
  • Plinth90%
  • Stilt Floor25%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A4

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A5

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsAS PER PLAN0%
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PLAN0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingAS PER PLAN0%
  • Street LightingAS PER PLAN0%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER PLAN0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingAS PER PLAN0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

34 documents held by Deedo, 75 filings listed on MahaRERA's project page

Others

Title

Encumbrances

Commencement certificates

Form b

Allotment letters

Registration certificate

Form 2s

Form 1s

Layout plan

Building plans

Document library

  • Other – LegalSteel Arrow_LLP Agreement.pdf · uploaded 8 May 2024View
  • Other – LegalSteel Arrow_LLP Certificate.pdf · uploaded 8 May 2024View
  • Other – FinanceSteel Arrow_LLP Certificate.pdf · uploaded 8 May 2024View
  • Declaration in FORM BSteel Arrow_Form B.pdf · uploaded 31 May 2024View
  • Other – LegalSteel_Purchase Deed 310524.pdf · uploaded 31 May 2024View
  • Other – FinanceSteel Arrow_LLP Agreement.pdf · uploaded 31 May 2024View
  • Copy of the legal title reportSteel Arrow_Search Report 300524.pdf · uploaded 31 May 2024View
  • Copy of Layout Approval (in case of layout)Steel_NA Order.pdf · uploaded 31 May 2024View
  • Building Plan Approval / NA Order for plotted developmentSteel_Sanction Map 1.pdf · uploaded 31 May 2024View
  • Building Plan Approval / NA Order for plotted developmentSteel_Sanction Map 2.pdf · uploaded 31 May 2024View
  • Commencement Certificates / NA Order for plotted developmentSteel_Commencement Certificate.pdf · uploaded 31 May 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsSteel Arrow_Other Disclosure Subhash.pdf · uploaded 31 May 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsSteel Arrow_Shankar Harwani.pdf · uploaded 31 May 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSteel Arrow_Bank format.pdf · uploaded 31 May 2024View
  • Proforma of Agreement for saleSteel Arrow_ATS.pdf · uploaded 31 May 2024View
  • a Details of encumbrances concerned to FinanceSteel Arrow_Encumberance.pdf · uploaded 31 May 2024View
  • b Details of encumbrances concerned to LegalSteel Arrow_Encumberance.pdf · uploaded 31 May 2024View
  • Declaration about Commencement CertificateSteel Arrow_CC declaration.pdf · uploaded 31 May 2024View
  • Deviation Report with respect to Allotment letterSteel Arrow_Deviation Allotment.pdf · uploaded 31 May 2024View
  • Deviation Report with respect to model copy of AgreementSteel Arrow_Deviation AFS.pdf · uploaded 31 May 2024View
  • Proforma of Allotment letterSteel_Allotment.pdf · uploaded 31 May 2024View
  • Other – TechnicalSteel Arrow_OPOR.pdf · uploaded 31 May 2024View
  • Other – TechnicalSteel Arrow_Mail.pdf · uploaded 31 May 2024View
  • CERSAI detailsSteel_Cersai 060624.pdf · uploaded 6 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Steel_Form 1_300624.pdf · uploaded 16 Jul 2024View
  • Disclosure of sold/ booked inventorySteel_Soldunsold_300624.pdf · uploaded 16 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Steelarrow Cityland ENG CERTFICATE_Form 2 Q1 24-25_compressed.pdf · uploaded 16 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Steelarrow Cityland ARC CERTFICATE_Form 1 Q2 24-25.pdf · uploaded 23 Oct 2024Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Steelarrow Cityland ENG CERTFICATE_Form 2 Q2 24-25.pdf · uploaded 23 Oct 2024Source
  • Disclosure of sold/ booked inventorySteelarrow Cityland SOLD UNSOLD INVENTORY _Q2_24-25.pdf · uploaded 23 Oct 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Steelarrow Cityland ARC CERTFICATE_Form 1 Q3 24-25.pdf · uploaded 17 Feb 2025Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Steelarrow Cityland Eng CERTFICATE_Form 1 Q3 24-25.pdf · uploaded 17 Feb 2025Source
  • Disclosure of sold/ booked inventorySteelarrow Cityland SOLD UNSOLD INVENTORY _Q3_24-25.pdf · uploaded 17 Feb 2025Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Steelarrow Cityland ARC CERTFICATE_Form 1 Q4 24-25.pdf · uploaded 26 Apr 2025Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Steelarrow Cityland Eng CERTFICATE_Form 1 Q4 24-25.pdf · uploaded 26 Apr 2025Source
  • Disclosure of sold/ booked inventorySteelarrow Cityland SOLD UNSOLD INVENTORY _Q4_24-25.pdf · uploaded 26 Apr 2025Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Steelarrow Cityland Quality Assurance Cert Q4 24-25.pdf · uploaded 26 Apr 2025Source
  • Form 1Steel_Form 1_300624.pdf · uploaded 20 Aug 2025View
  • Form 2Steelarrow Cityland ENG CERTFICATE_Form 2 Q1 24-25.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventorySteel_Soldunsold_300624.pdf · uploaded 20 Aug 2025View
  • Form 1Steelarrow Cityland ARC CERTFICATE_Form 1 Q2 24-25.pdf · uploaded 20 Aug 2025Source
  • Form 2Steelarrow Cityland ENG CERTFICATE_Form 2 Q2 24-25.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventorySteelarrow Cityland SOLD UNSOLD INVENTORY _Q2_24-25.pdf · uploaded 20 Aug 2025Source
  • Form 1Steelarrow Cityland ARC CERTFICATE_Form 1 Q3 24-25.pdf · uploaded 20 Aug 2025Source
  • Form 2Steelarrow Cityland Eng CERTFICATE_Form 1 Q3 24-25.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventorySteelarrow Cityland SOLD UNSOLD INVENTORY _Q3_24-25.pdf · uploaded 20 Aug 2025Source
  • Form 1Steelarrow Cityland ARC CERTFICATE_Form 1 Q4 24-25.pdf · uploaded 20 Aug 2025Source
  • Form 2Steelarrow Cityland Eng CERTFICATE_Form 1 Q4 24-25.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventorySteelarrow Cityland SOLD UNSOLD INVENTORY _Q4_24-25.pdf · uploaded 20 Aug 2025Source
  • Form 1GOVINDA ARCADE ARC CERF.pdf · uploaded 20 Aug 2025Source
  • Form 2GOVINDA ARCADE ENG CERF.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventoryGOVINDA ARCADE INVENTORY.pdf · uploaded 20 Aug 2025Source
  • Form 1GOVINDA ARCADE ARC CERF_Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Form 2GOVINDA ARCADE ENG CERF_Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Disclosure of Sold and Booked InventoryGOVINDA ARCADE INVENTORY_Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Form 1GOVINDA ARCADE ARC CERF_Q3 25-26.pdf · uploaded 27 Feb 2026Source
  • Form 2GOVINDA ARCADE ENG CERF_Q3 25-26.pdf · uploaded 27 Feb 2026View
  • Disclosure of Sold and Booked InventoryGOVINDA ARCADE INVENTORY_Q3 25-26.pdf · uploaded 27 Feb 2026View
  • Form 1GOVINDA ARCADE ARC CERF_Q4 25-26.pdf · uploaded 27 May 2026View
  • Form 2GOVINDA ARCADE ENG CERF_Q4 25-26.pdf · uploaded 27 May 2026View
  • Disclosure of Sold and Booked InventoryGOVINDA ARCADE Sold Unsold INVENTORY_Q4 25-26.pdf · uploaded 27 May 2026View
  • Form 1Steel Arrow_Form 1_300626.pdf · uploaded 21 Aug 2026View
  • Form 2Steel Arrow_Form 2_300626.pdf · uploaded 21 Aug 2026View
  • Disclosure of Sold and Booked InventorySteel Arrow_Sold Unsold_300626.pdf · uploaded 21 Aug 2026View

Promoter documents

  • Declaration Form BSteel Arrow_Form B.pdf · uploaded 31 May 2024View
  • Legal Title reportSteel Arrow_Search Report 300524.pdf · uploaded 31 May 2024View

Technical documents

  • Layout ApprovalSteel_NA Order.pdfView
  • Building Plan ApprovalSteel_Sanction Map 1.pdfView
  • Building Plan ApprovalSteel_Sanction Map 2.pdfView

Other legal documents

  • Other – LegalSteel_Purchase Deed 310524.pdfView
  • Other – LegalSteel Arrow_LLP Agreement.pdfView
  • Other – LegalSteel Arrow_LLP Certificate.pdfView

Financial documents

  • Other – FinanceSteel Arrow_LLP Certificate.pdf · uploaded 8 May 2024View
  • Other – FinanceSteel Arrow_LLP Agreement.pdf · uploaded 31 May 2024View

Proforma allotment letter

  • Proforma allotment letterSteel_Allotment.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nandgaon peth, Amravati taluka

Survey, CTS, gat or plot numbers

458/1458/1458/2458/2459459460/1460/1460/1 C460/1-C460/2460/2460/3460/3461/1461/1461/1/A/2461/1/A/2461/1/A MOUJE BORGAON DHARMALE461/1/A MOUJE BORGAON DHARMALE461/2461/2463/1/A/1463/1/A/1463/1/A/3463/1/A/3463/1/C463/1/C464/1464/1464/2464/2464/3464/37777795NANDGAONPETH PART 2 PRANGANE NANDGAONNANDGAONPETH PART 2 PRANGANE NANDGAON PETHPLOT NO 795 S NO76PLOT NO 795 S NO76

As published on MahaRERA's project page

PLOT NO 795 S NO76,77,459,460/1,460/1-C,460/2,460/3,461/2,458/1,458/2,464/1,464/2,464/3,463/1/A/1,461/1/A/2,463/1/A/3,463/1/C,461/1 AND 461/1/A MOUJE BORGAON DHARMALE AND NANDGAONPETH PART 2 PRANGANE NANDGAON PETH

Boundaries

North
Shet Survey No 463-1-K And 461-1
South
18 Mtr Dp Road
East
Layout Plot No 796
West
Layout Amenity Plot No 800

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrakash Chandak—
Chartered accountantCa Deepak Zambani Gad And Associates—
EngineerPankaj Vinodkumar Bajaj—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology