Chaturbhuj Residency

Lapsed

Malkapur (Ct), Akola 444002 |Promoter: Manoj Prabhakar Mahajan

Residential / Group HousingRERAP50100033689
2 Mar 2022Registered with MahaRERA
8 Feb 2023Promised completion
1Building
16Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
1
Unit types
2BHK16 units in all
Land area for this project
479 sq m (5,160 sq ft)
Permissible built-up area
1,177 sq m (12,664 sq ft)
Sanctioned built-up area
1,177 sq m (12,664 sq ft)
Address
Plot no 63 Survey No 10/3, Ring Road, Ramkrishna NagarPIN 444002
Designated bank account
Yes Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.68395, 77.02547
Chaturbhuj Residency is at latitude 20.68395, longitude 77.02547.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 8 Feb 2023

The latest completion date on record passed 3 years and 8 months ago.

Registered
2 Mar 2022
Promised
8 Feb 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P501000336892 Mar 20228 Feb 2023—Manoj Prabhakar MahajanProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Chaturbhuj Residency616

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

16 units registered

2BHK · 16 units
TypeCarpet areaUnits
2BHK56.67 sq m · 610 sq ft4
2BHK56.77 sq m · 611 sq ft4
2BHK58.42 sq m · 629 sq ft8

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000038
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Chaturbhuj Residency

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supplyconstruction not started yet0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)construction not started yet0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingconstruction not started yet0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

14 documents held by Deedo, 18 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificates

Allotment letters

Form b

Others

Registration certificate

Layout plans

Building plan

Document library

  • Copy of the legal title report2 Search report.pdf · uploaded 10 Feb 2022View
  • Details of encumbrances3 Encumbrances.PDF · uploaded 10 Feb 2022View
  • Commencement Certificates / NA Order for plotted development6 COMMENCEMENT CERTIFCATE M-1.pdf · uploaded 10 Feb 2022View
  • Proforma of Allotment letter20 A Aggrement ot Sale.pdf · uploaded 10 Feb 2022View
  • Proforma of Allotment letter20 B Allotment.PDF · uploaded 10 Feb 2022View
  • CERSAI detailsUndertaking.pdf · uploaded 14 Feb 2022View
  • CERSAI detailsCERSAI_Search_Report_200229899935_For_Asset_Based_Search_09_02_2022_20_01_17_821.pdf · uploaded 14 Feb 2022View
  • Declaration about Commencement CertificateDeclaration Comm new.pdf · uploaded 14 Feb 2022View
  • Declaration in FORM BForm B_compressed (1).pdf · uploaded 14 Feb 2022View
  • Copy of Layout Approval (in case of layout)layout map.pdf · uploaded 21 Feb 2022View
  • Copy of Layout Approval (in case of layout)NA order.pdf · uploaded 21 Feb 2022View
  • Building Plan Approval / NA Order for plotted development5 Chaturbhuj sanction plan.pdf · uploaded 21 Feb 2022View

Promoter documents

  • Legal Title report2 Search report.pdf · uploaded 10 Feb 2022View
  • Declaration Form BForm B_compressed (1).pdf · uploaded 14 Feb 2022View

Technical documents

  • Layout Approvallayout map.pdfView
  • Layout ApprovalNA order.pdfView
  • Building Plan Approval5 Chaturbhuj sanction plan.pdfView

Proforma allotment letter

  • Proforma allotment letter20 B Allotment.PDFView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Malkapur (CT), Akola taluka

Survey, CTS, gat or plot numbers

10/363Plot no 63 Survey No 10/3

As published on MahaRERA's project page

Plot no 63 Survey No 10/3

Boundaries

North
Layout plot no 59
South
9 m Layout Road
East
Layout of Shree Kishorsing Bisen
West
Layout Plot no 62

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShraddha D Mahajan—
Chartered accountantPrathamesh A Bajaj—
EngineerSantosh A Masane—
OtherImran Khan—
OtherIrfan Khan—
OtherRahul Mali—
OtherRaju Nimbalkar—
OtherRamesh Warghat—
OtherSuraj Shingade—
OtherVirendra Bhade—

Source: MahaRERA project page. Contact details are not shown.