Shree Gajanan Residency

Completed

Akola (M Corp.), Akola 444002 |Promoter: Santosh Sudhakarrao Lokhande

Residential / Group HousingRERAP50100011187
31 Aug 2017Registered with MahaRERA
31 Mar 2018Promised completion
1Building
13Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
2 BHK13 units in all
Land area for this project
468 sq m (5,040 sq ft)
Permissible built-up area
1 sq m (15 sq ft)
Sanctioned built-up area
1 sq m (12 sq ft)
Address
15/138, Dabakiroad, DabkiroadPIN 444002
Designated bank account
Yes Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.96749, 79.29383
Shree Gajanan Residency is at latitude 19.96749, longitude 79.29383.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2018

The latest completion date on record passed 8 years and 7 months ago.

Registered
31 Aug 2017
Promised
31 Mar 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5010001118731 Aug 201731 Mar 2018—Santosh Sudhakarrao LokhandeProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shree Gajanan Residency413

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

13 units registered

2 BHK · 13 units
TypeCarpet areaUnits
2 BHK45 sq m · 484 sq ft13

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shree Gajanan Residency

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBoarwell100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Septic Tank100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

22 documents held by Deedo, 25 filings listed on MahaRERA's project page

Allotment letters

Titles

Encumbrance

Commencement certificate

Form 1

Form 2

Registration certificate

Form b

Form 5s

Form 4

Form 2as

Others

Layout plan

Building plan

Document library

  • Copy of the legal title reportSearch report 2.pdf · uploaded 13 Aug 2017View
  • Copy of the legal title reportSearch report2.pdf · uploaded 13 Aug 2017View
  • Copy of Layout Approval (in case of layout)NA Layout.pdf · uploaded 13 Aug 2017View
  • Building Plan Approval (IOD)Building Plan.pdf · uploaded 13 Aug 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Cert.pdf · uploaded 13 Aug 2017View
  • Proforma of Allotment letterIn Progress.pdf · uploaded 13 Aug 2017View
  • Details of encumbrancesencumbrance.pdf · uploaded 13 Aug 2017View
  • Declaration in FORM BIn Progress.pdf · uploaded 13 Aug 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 13 Aug 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Cert.pdf · uploaded 13 Aug 2017View
  • Declaration in FORM BForm B Lokhande.pdf · uploaded 28 Dec 2017View
  • Proforma of Allotment letterpart 1.pdf · uploaded 10 Apr 2018View
  • Proforma of Allotment letterpart 2.pdf · uploaded 10 Apr 2018View
  • Certificates of CA (Form 5)jpg2pdf.pdf · uploaded 7 Apr 2019View
  • Certificates of Architect (Form 4)form.pdf · uploaded 10 Jun 2019View
  • Form 2Aform 2A - 1.pdf · uploaded 30 Jun 2019View
  • Form 2AForm 2A - 2.pdf · uploaded 30 Jun 2019View
  • Certificates of CA (Form 5)Form 5-converted.pdf · uploaded 30 Jun 2019View

Promoter documents

  • Legal Title reportSearch report 2.pdf · uploaded 13 Aug 2017View
  • Legal Title reportSearch report2.pdf · uploaded 13 Aug 2017View
  • Declaration Form BIn Progress.pdf · uploaded 13 Aug 2017View
  • Declaration Form BForm B Lokhande.pdf · uploaded 28 Dec 2017View

Technical documents

  • Layout ApprovalNA Layout.pdfView
  • Building Plan ApprovalBuilding Plan.pdfView

Proforma allotment letter

  • Proforma allotment letterpart 2.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Akola (M Corp.), Akola taluka

Survey, CTS, gat or plot numbers

15/138

As published on MahaRERA's project page

15/138

Boundaries

North
9 Mtr Road
South
Plot No 37
East
Service Line
West
18 Mtr Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAjay K Tayde—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology