BLD_007037Completed6 floors
Wing A · Prime Tower
Akola (M Corp.) · RERA P50100033195
6Sanctioned habitable floorsregistration certificate
31 Jan 2024Revised completionpromised 31 Jan 2023
Floors
6 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P50100033195 · registered 9 Feb 2022
- Promised completion
- 31 Jan 2023
- Revised completion
- 31 Jan 2024
- Sanctioned habitable floors
- 6
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 31.3 m² (337 sq.ft) | 2 | not published |
| 1BHK | 38.4 m² (413 sq.ft) | 2 | not published |
| 1BHK | 40.8 m² (439 sq.ft) | 2 | not published |
| 1BHK | 47.6 m² (512 sq.ft) | 4 | not published |
| 1BHK | 56.1 m² (604 sq.ft) | 4 | not published |
| 1BHK | 58.6 m² (631 sq.ft) | 2 | not published |
| Shop | 15.9 m² (171 sq.ft) | 2 | not published |
| Shop | 19.1 m² (206 sq.ft) | 8 | not published |
| Shop | 19.8 m² (213 sq.ft) | 1 | not published |
| Shop | 20.6 m² (222 sq.ft) | 6 | not published |
| Shop | 27.1 m² (291 sq.ft) | 2 | not published |
| Shop | 28.6 m² (308 sq.ft) | 1 | not published |
| Shop | 36 m² (387 sq.ft) | 1 | not published |
| Shop | 41.1 m² (442 sq.ft) | 1 | not published |
| Shop | 42.4 m² (456 sq.ft) | 2 | not published |
| Shop | 71 m² (764 sq.ft) | 1 | not published |
| Total | 41 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 12 |
| Open Space | 0 | 0 | 0 | 0 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor0%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology