Akola (M Corp.), Akola 444001 |Promoter: Pankaj Rameshchandra Kothari

Residential / Group HousingRERAP50100033083
3 Feb 2022Registered with MahaRERA
31 Dec 2026Promised completion
6Buildings
1MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
6
Land area for this project
5,885 sq m (63,341 sq ft)
Permissible built-up area
30,306 sq m (3,26,207 sq ft)
Sanctioned built-up area
19,751 sq m (2,12,601 sq ft)
Recreational open space
624 sq m (6,718 sq ft)
Planning authority
Akola Municipal Corporation
Address
17/1/A, Behind Tulshan Bunglows, Geeta NagarPIN 444001
Designated bank account
Akola Janata Commercial Cooperative Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.68866, 76.99309
Lotus Green is at latitude 20.68866, longitude 76.99309.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2026

Registered
3 Feb 2022
Promised
31 Dec 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P501000330833 Feb 202231 Dec 2026—Pankaj Rameshchandra KothariProject page

6 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A18—
A28—
A38—
B18—
C18—
C28—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
A1Closed/Covered131000131
A1Open Space00000
A2Closed/Covered131000131
A2Open Space00000
A3Closed/Covered1101000120
A3Open Space00000
B1Closed/Covered982400122
B1Open Space00000
C1Closed/Covered36300066
C1Open Space00000
C2Closed/Covered39300069
C2Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

A1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.—

A2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

A3

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

B1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

C1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

C2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsFootpaths100%
  • Water SupplyTap Water100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Septic tank100%
  • Storm Water DrainsStorm Water Drains100%
  • Landscaping & Tree PlantingTree Plantation100%
  • Street LightingStreet Lighting100%
  • Community BuildingsHall100%
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRain Water Harvesting100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsFire Extinguisher100%
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceGarden and Temple100%
  • Open ParkingOpen Parking100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

49 documents held by Deedo, 72 filings listed on MahaRERA's project page

Encumbrance

Commencement certificates

Form b

Titles

Others

Form 5s

Form 1s

Form 2s

Form 2as

Registration certificate

Layout plan

Building plans

Allotment letter

Document library

  • Details of encumbrancesEncumberance.pdf · uploaded 2 Jan 2022View
  • Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 2 Jan 2022View
  • Building Plan Approval / NA Order for plotted developmentSanction Plan.pdf · uploaded 2 Jan 2022View
  • Commencement Certificates / NA Order for plotted developmentCommencement Cert.pdf · uploaded 2 Jan 2022View
  • Declaration in FORM BForm B Declaration.pdf · uploaded 2 Jan 2022View
  • Copy of the legal title reportLSR.pdf · uploaded 24 Jan 2022View
  • Copy of the legal title reportLSR Documents.pdf · uploaded 24 Jan 2022View
  • Copy of the legal title reportLSR Documents 1.pdf · uploaded 24 Jan 2022View
  • Copy of the legal title reportLSR Documents 2.pdf · uploaded 24 Jan 2022View
  • Copy of the legal title reportLSR Documents 3.pdf · uploaded 24 Jan 2022View
  • Proforma of Allotment letterDraft Allotment letter along with Agreenment to sale.pdf · uploaded 24 Jan 2022View
  • CERSAI detailsCERSAI_Search_Report_200228662781_For_Asset_Based_Search_24_01_2022_16_46_15_594.pdf · uploaded 24 Jan 2022View
  • Declaration about Commencement CertificateDeclaration about commencement certificate.pdf · uploaded 27 Jan 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 21-22.pdf · uploaded 24 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)LG FROM 5.pdf · uploaded 20 Oct 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 03-02-22 TO 31-03-22.pdf · uploaded 25 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 01-04-22 TO 30-06-22.pdf · uploaded 25 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 01-07-22 TO 30-09-22.pdf · uploaded 25 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 01-10-22 TO 31-12-22.pdf · uploaded 25 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 01-01-23 TO 31-03-23.pdf · uploaded 25 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 01-04-23 TO 30-06-23.pdf · uploaded 25 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 01-07-23 TO 30-09-23.pdf · uploaded 25 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 01-10-23 TO 31-12-23.pdf · uploaded 25 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 01-01-24 TO 31-03-24.pdf · uploaded 25 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 03-02-22 to 31-03-22.pdf · uploaded 25 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2 01-04-22 to 30-06-22.pdf · uploaded 25 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2 01-07-22 to 30-09-22.pdf · uploaded 25 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 01-10-22 to 30-12-22.pdf · uploaded 25 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 01-01-23 to 31-03-23.pdf · uploaded 25 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 01-04-23 to 30-06-23.pdf · uploaded 25 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 01-07-23 to 30-09-23.pdf · uploaded 25 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 01-10-23 to 31-12-23.pdf · uploaded 25 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 01-01-24 to 31-03-24.pdf · uploaded 25 Apr 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 23-24.pdf · uploaded 30 Oct 2024View
  • Form 2A (FY 2022-2023)LG 31-03-2023.pdf · uploaded 29 Sep 2025View
  • Form 2A (FY 2023-2024)LG 31-03-2024.pdf · uploaded 29 Sep 2025Source
  • Form 2A (FY 2024-2025)LG 31-03-2025.pdf · uploaded 29 Sep 2025Source
  • Form 1Form 1 310325.pdf · uploaded 29 Sep 2025View
  • Form 2Form 2 310325.pdf · uploaded 29 Sep 2025View
  • Disclosure of Sold and Booked InventorySold Unsold 310325.pdf · uploaded 29 Sep 2025View
  • Withdrawal Update Form 1Form 1 310325.pdf · uploaded 29 Sep 2025View
  • Withdrawal Update Form 2Form 2 01-01-24 to 31-03-24.pdf · uploaded 29 Sep 2025View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 2 Oct 2025View
  • Withdrawal Update Form 2Form 2.pdf · uploaded 2 Oct 2025View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 17 Oct 2025View
  • Withdrawal Update Form 2Form 2.pdf · uploaded 17 Oct 2025View
  • Form 5 (FY 2024-2025)From 5 LG.pdf · uploaded 10 Jan 2026View
  • Form 2A (FY 2021-2022)Form 2A.pdf · uploaded 12 Jan 2026View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 6 Jun 2026View
  • Withdrawal Update Form 2Form 2.pdf · uploaded 6 Jun 2026View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 6 Jun 2026View
  • Withdrawal Update Form 2Form 2.pdf · uploaded 6 Jun 2026View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 2 Oct 2026View
  • Withdrawal Update Form 2Form 2.pdf · uploaded 2 Oct 2026View
  • Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 2 Oct 2026View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 2 Oct 2026View
  • Withdrawal Update Form 2Form 2.pdf · uploaded 2 Oct 2026View
  • Form 5 (FY 2025-2026)From 5 LG.pdf · uploaded 2 Oct 2026View
  • Occupational CertificateOC.pdf · uploaded 2 Oct 2026View
  • Occupational CertificateOC Mail.pdf · uploaded 2 Oct 2026View

Promoter documents

  • Declaration Form BForm B Declaration.pdf · uploaded 2 Jan 2022View
  • Legal Title reportLSR.pdf · uploaded 24 Jan 2022View
  • Legal Title reportLSR Documents.pdf · uploaded 24 Jan 2022View
  • Legal Title reportLSR Documents 1.pdf · uploaded 24 Jan 2022View
  • Legal Title reportLSR Documents 2.pdf · uploaded 24 Jan 2022View
  • Legal Title reportLSR Documents 3.pdf · uploaded 24 Jan 2022View
  • Legal Title reportTitle Report.pdf · uploaded 26 Feb 2026View

Technical documents

  • Layout ApprovalLayout Approval.pdfView
  • Building Plan ApprovalSanction Plan.pdfView
  • Building Plan ApprovalNEW SANCTION MAP.pdfView

Commencement certificates and NA orders

  • Commencement certificate / NA orderSource

Proforma allotment letter

  • Proforma allotment letterDraft Allotment letter along with Agreenment to sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Akola (M Corp.), Akola taluka

Survey, CTS, gat or plot numbers

17/1/A

As published on MahaRERA's project page

17/1/A

Boundaries

North
Land of Mukinda
South
Land of Daulat Kalore
East
Land of Rukhminibai B Kalore and others
West
Land of Tulsiram Kale

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr. Kamlesh Kriplani—
Chartered accountantAgrawal Bajoria Padiya & Associates—
Chartered accountantP.c.bhandari & Co.—
EngineerEr. Dhyanesh Dahatonde—
EngineerPradeep R Agrawal—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology