BLD_006992Completed5 floors
Landmark Tower · Landmark
Akola (M Corp.) · RERA P50100023563
5Sanctioned habitable floorsregistration certificate
30 Mar 2024Promised completion
Floors
5 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- Sanctioned habitable floors
- 5
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 73.3 m² (789 sq.ft) | 1 | not published |
| 1BHK | 73.3 m² (789 sq.ft) | 1 | not published |
| 1BHK | 79.8 m² (859 sq.ft) | 1 | not published |
| 1BHK | 79.8 m² (859 sq.ft) | 1 | not published |
| 1BHK | 83.6 m² (900 sq.ft) | 1 | not published |
| 1BHK | 83.6 m² (900 sq.ft) | 1 | not published |
| 1BHK | 102.6 m² (1,104 sq.ft) | 1 | not published |
| 1BHK | 102.6 m² (1,104 sq.ft) | 1 | not published |
| Shop | 21.2 m² (228 sq.ft) | 1 | not published |
| Shop | 22 m² (237 sq.ft) | 1 | not published |
| Shop | 22.1 m² (238 sq.ft) | 1 | not published |
| Shop | 22.5 m² (242 sq.ft) | 1 | not published |
| Shop | 22.9 m² (246 sq.ft) | 1 | not published |
| Shop | 23.4 m² (252 sq.ft) | 1 | not published |
| Shop | 27.9 m² (300 sq.ft) | 1 | not published |
| Shop | 28.5 m² (307 sq.ft) | 1 | not published |
| Shop | 33.1 m² (357 sq.ft) | 1 | not published |
| Shop | 33.7 m² (363 sq.ft) | 1 | not published |
| Shop | 33.7 m² (363 sq.ft) | 1 | not published |
| Shop | 35.5 m² (382 sq.ft) | 1 | not published |
| Shop | 45.5 m² (490 sq.ft) | 1 | not published |
| Shop | 45.9 m² (494 sq.ft) | 1 | not published |
| Shop | 46.5 m² (501 sq.ft) | 1 | not published |
| Shop | 46.7 m² (502 sq.ft) | 1 | not published |
| Shop | 47.2 m² (508 sq.ft) | 1 | not published |
| Shop | 63.5 m² (683 sq.ft) | 1 | not published |
| Shop | 66.5 m² (716 sq.ft) | 1 | not published |
| Total | 27 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 122 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor0%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology