Skip to content
Deedo home
Menu

IT Square

Completed

Akola (M Corp.), Akola 444001 |Promoter: S S Enterprises

18 Dec 2019Registered with MahaRERA
21 May 2023Promised completion
1Building
65Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Completed
Buildings
1
Unit types
Hall, Office space, Shop65 units in all
Land area for this project
1,917 sq m (20,631 sq ft)
Permissible built-up area
5,587 sq m (60,138 sq ft)
Sanctioned built-up area
5,587 sq m (60,138 sq ft)
Address
Survey No. 10 plus 11, Layout Plot No.59 and 60, Nazul Plot No.6/1, 7/1, 12, 13, 14/49 and 14/50, Nazul Sheet no.68/80, Chhatrapati Shivaji Maharaj Chowk, , Gorakshan Road, AkolaPIN 444001
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 21 May 2023

The latest completion date on record passed 3 years and 5 months ago.

Registered
18 Dec 2019
Promised
21 May 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5010002351818 Dec 201921 May 2023—S S EnterprisesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
IT Sqaure865

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

65 units registered

Hall · 1 unitOffice space · 16 unitsShop · 48 units
TypeCarpet areaUnits
Hall169.32 sq m · 1,823 sq ft1
Office space30.55 sq m · 329 sq ft1
Office space31.93 sq m · 344 sq ft1
Office space78.11 sq m · 841 sq ft2
Office space81.39 sq m · 876 sq ft1
Office space85.75 sq m · 923 sq ft1
Office space89.26 sq m · 961 sq ft4
Office space89.89 sq m · 968 sq ft2
Office space101.35 sq m · 1,091 sq ft2
Office space103.57 sq m · 1,115 sq ft2
Shop13.11 sq m · 141 sq ft1
Shop17.05 sq m · 184 sq ft1
Shop19.62 sq m · 211 sq ft5
Shop19.88 sq m · 214 sq ft1
Shop22.2 sq m · 239 sq ft3
Shop25.17 sq m · 271 sq ft5
Shop25.5 sq m · 274 sq ft1
Shop26.24 sq m · 282 sq ft1
Shop30.09 sq m · 324 sq ft3
Shop30.14 sq m · 324 sq ft3
Shop36.53 sq m · 393 sq ft2
Shop42.95 sq m · 462 sq ft2
Shop45.2 sq m · 487 sq ft5
Shop45.81 sq m · 493 sq ft1
Shop49.8 sq m · 536 sq ft2
Shop53.61 sq m · 577 sq ft5
Shop54.34 sq m · 585 sq ft1
Shop57.46 sq m · 618 sq ft2
Shop64.58 sq m · 695 sq ft1
Shop82.09 sq m · 884 sq ft2
Shop110 sq m · 1,184 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

IT Sqaure

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Septic Tanks100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingLandscaping100%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRain Water Harvesting100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsFire Protection100%
  • Electrical meter room, sub-station, receiving stationMeter Room100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

24 documents held by Deedo, 35 filings listed on MahaRERA's project page

Title

Encumbrance

Form b

Commencement certificates

Form 2as

Others

Form 5

Registration certificate

Form 4s

Layout plan

Building plans

Allotment letter

Document library

  • Copy of the legal title reportLegal search Report.pdf · uploaded 14 Dec 2019View
  • Details of encumbrancesencumberance.pdf · uploaded 14 Dec 2019View
  • Building Plan Approval / NA Order for plotted developmentSanction Map.pdf · uploaded 14 Dec 2019View
  • Building Plan Approval / NA Order for plotted developmentSanction Map 1.pdf · uploaded 14 Dec 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certrificate.pdf · uploaded 14 Dec 2019View
  • Declaration in FORM BForm B Declaration.pdf · uploaded 14 Dec 2019View
  • Proforma of Allotment letterAgreenment to sale.pdf · uploaded 14 Dec 2019View
  • OtherCredia membership.pdf · uploaded 14 Dec 2019View
  • Copy of Layout Approval (in case of layout)Commencement Certrificate.pdf · uploaded 14 Dec 2019View
  • Building Plan Approval / NA Order for plotted developmentSanction MAP.pdf · uploaded 13 Jul 2021View
  • Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf · uploaded 13 Jul 2021View
  • Commencement Certificates / NA Order for plotted developmentCommencement certificate.pdf · uploaded 13 Jul 2021View
  • Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD.pdf · uploaded 13 Jul 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)CA Annual Certificate.PDF · uploaded 13 Jul 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Dec-2019.pdf · uploaded 13 Jul 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)March-2020.pdf · uploaded 13 Jul 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)June-2020.pdf · uploaded 13 Jul 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sept-2020.pdf · uploaded 13 Jul 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Dec-2020.pdf · uploaded 13 Jul 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)March-2021.pdf · uploaded 13 Jul 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CA Annual Certificate 20-21.PDF · uploaded 22 Oct 2021Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 21-22.pdf · uploaded 11 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 21-22.pdf · uploaded 11 Feb 2023Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate.pdf · uploaded 11 Feb 2023Source
  • Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 11 Feb 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentATC FULL OCC.pdf · uploaded 7 Oct 2023Source
  • Architect’s Certificate on Completion of Project (Form 4)Form 4 New .pdf · uploaded 7 Oct 2023View

Promoter documents

  • Legal Title reportLegal search Report.pdf · uploaded 14 Dec 2019View
  • Declaration Form BForm B Declaration.pdf · uploaded 14 Dec 2019View

Technical documents

  • Building Plan ApprovalSanction Map.pdfView
  • Building Plan ApprovalSanction Map 1.pdfView
  • Layout ApprovalCommencement Certrificate.pdfView
  • Building Plan ApprovalSanction MAP.pdfView

Other legal documents

  • OtherCredia membership.pdfView

Proforma allotment letter

  • Proforma allotment letterAgreenment to sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Akola (M Corp.), Akola taluka

Survey, CTS, gat or plot numbers

1212131314/4914/4914/5014/505960606/17/17/1Layout Plot No.59Nazul Plot No.6/1Nazul Sheet no.68/80Survey No. 10 plus 11

As published on MahaRERA's project page

Survey No. 10 plus 11, Layout Plot No.59 and 60, Nazul Plot No.6/1, 7/1,12,13,14/49 and 14/50, Nazul Sheet no.68/80

Boundaries

North
Service Lane
South
Government Road
East
Plot No 61
West
Layout Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMegha Laddha—
Chartered accountantAgrawal Bajoria Padiya & Associates—
EngineerAnuraj S Agrawal—
OtherNusrart Khan—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology