BLD_007077Promised date passed4 floors

A · Citycon Arcade And Theatre

Akola (M Corp.) · RERA P50100049932

4Sanctioned habitable floorsregistration certificate
30 Dec 2025Promised completion

Floors

4 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P50100049932 · registered 6 Mar 2023
Promised completion
30 Dec 2025
Sanctioned habitable floors
4

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1RK20.4 m² (220 sq.ft)1not published
1RK21.5 m² (232 sq.ft)1not published
1RK22.8 m² (245 sq.ft)1not published
1RK24.8 m² (267 sq.ft)4not published
1RK26.2 m² (282 sq.ft)2not published
1RK38.5 m² (414 sq.ft)1not published
Shop12.4 m² (133 sq.ft)1not published
Shop20.4 m² (220 sq.ft)2not published
Shop21.5 m² (231 sq.ft)2not published
Shop22.5 m² (242 sq.ft)2not published
Shop24.5 m² (264 sq.ft)8not published
Shop25.8 m² (278 sq.ft)3not published
Shop25.8 m² (278 sq.ft)2not published
Shop38.8 m² (418 sq.ft)1not published
Total31

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered0000
Open Space0000

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure85%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology