Mauli Green Park

Completion due Jun 2028

Supa, Ahmednagar 414301 |Promoter: Mauli Developers

7 Nov 2020Registered with MahaRERAFirst of 2 registrations
30 Jun 2028Promised completionLatest across registrations
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.95255, 74.54249
Mauli Green Park is at latitude 18.95255, longitude 74.54249.

Also registered as

Mauli Green Park Phase-1Mauli Green Park Phase-2
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2028

P52200026981
Registered
7 Nov 2020
Promised
30 Jun 2028

Completion promised for 1 Nov 2025

P52200032285

The latest completion date on record passed 11 months ago.

Registered
22 Dec 2021
Promised
1 Nov 2025

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P522000269817 Nov 202030 Jun 2028—Mauli DevelopersProject page
P5220003228522 Dec 20211 Nov 2025—Mauli DevelopersProject page

Documents

2 documents held by Deedo

Registration certificates

  • Registration certificateP52200026981 · 7 Nov 2020ViewSource
  • Registration certificateP52200032285 · 22 Dec 2021ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Supa

Survey, CTS, gat or plot numbers

47/2

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology