Skip to content

Wing D · Patni Commercial Complex Phase-4

Washim (M Cl) · RERA P50200003441

IDBLD_0538406 floorsPromised date passed
6Sanctioned habitable floorsregistration certificate
30 Jun 2026Revised completionpromised 30 Jun 2026
44 of 258Units bookedMahaRERA project page

Floors

6 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P50200003441 · registered 5 Aug 2017
Promised completion
30 Jun 2026
Revised completion
30 Jun 2026
Sanctioned habitable floors
6
ProjectId
283
ProjectName
PATNI COMMERCIAL COMPLEX PHASE-4
TotalUnitCount
0
ProjectBuildingId
81,106
BuildingNameNumber
WING D
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P50200003441
ProjectBuildingWingsId
81,106
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
WING D
NoOfBuildingWingFloorProposed
6
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
6

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
SHOP35.1 m² (378 sq.ft)16444
SHOP67.8 m² (730 sq.ft)40
SHOP119.7 m² (1,288 sq.ft)40
SHOP PROPOSED35.1 m² (378 sq.ft)820
SHOP PROPOSED67.8 m² (730 sq.ft)20
SHOP PROPOSED119.7 m² (1,288 sq.ft)20
Total25844
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology