Vastuvishwa Apartments, Bapatwadi

Lapsed

Wardha (M Cl), Wardha 442001 |Promoter: RSV Realities

1 Sep 2017Registered with MahaRERA
31 Mar 2019Promised completion
5 Feb 2023Revised completionPushed back 3 years and 11 months
1Building
14Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Lapsed
Buildings
1
Unit types
Residential Commerci14 units in all
Land area for this project
608 sq m (6,539 sq ft)
Permissible built-up area
783 sq m (8,428 sq ft)
Sanctioned built-up area
783 sq m (8,428 sq ft)
Address
Plot No 5, 6PIN 442001
Designated bank account
Bank Of Baroda
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.58175, 73.98171
Vastuvishwa Apartments, Bapatwadi is at latitude 18.58175, longitude 73.98171.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years and 11 months

The latest completion date on record passed 3 years and 8 months ago.

Registered
1 Sep 2017
Promised
31 Mar 2019
Revised
5 Feb 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P504000120801 Sep 201731 Mar 20195 Feb 2023RSV RealitiesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Vastuvishwa Apartments, Wardha714

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

14 units registered

Residential Commerci · 14 units
TypeCarpet areaUnits
Residential Commerci580.07 sq m · 6,244 sq ft14

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Vastuvishwa Apartments, Wardha

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyDone100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Done100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingDone100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsDone100%
  • Electrical meter room, sub-station, receiving stationDone100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingAvailable on Front of Building1%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

29 documents held by Deedo, 34 filings listed on MahaRERA's project page

Title

Encumbrances

Form b

Form 1

Form 2

Allotment letters

Registration certificate

Commencement certificates

Form 5s

Form 2as

Others

Extension certificate

Layout plan

Building plan

Document library

  • Declaration in FORM B6.pdf · uploaded 31 Jul 2017View
  • Details of encumbrances2.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)13.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title report1.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)9.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterProforma - Allotment Letter.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)3.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterAgreement to Sell.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement_Certificate.pdf · uploaded 31 Mar 2018View
  • Commencement Certificates / NA Order for plotted developmentCommencement_Certificate.pdf · uploaded 31 Mar 2018View
  • Commencement Certificates / NA Order for plotted developmentCommencement_Certificate.pdf · uploaded 31 Mar 2018View
  • Commencement Certificates / NA Order for plotted developmentCommencement_Certificate.pdf · uploaded 10 Apr 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)IT Returns-2017-18.pdf · uploaded 19 Aug 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)IT Returns-2018-19.pdf · uploaded 19 Aug 2021Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)IT Returns-2019-20.pdf · uploaded 19 Aug 2021View
  • Declaration about Commencement Certificateapplication for grant of completion and occupation certificate-converted-compressed (1).pdf · uploaded 19 Aug 2021View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentapplication for grant of completion and occupation certificate-converted-compressed (1).pdf · uploaded 19 Aug 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance Certificate by Engineer for 20-21.pdf · uploaded 29 Aug 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quality Assurance Certificate by Engineer for 2019-20.pdf · uploaded 29 Aug 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 by CA for 2017-18.pdf · uploaded 29 Aug 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 by CA for 2019-20.pdf · uploaded 29 Aug 2021View
  • Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory.pdf · uploaded 29 Aug 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 by CA for 2017-18.pdf · uploaded 29 Aug 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 by CA for 2018-19.pdf · uploaded 29 Aug 2021View
  • CERSAI detailsCERSAI_Search_Report_200240087348.pdf · uploaded 23 Sep 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 by CA for 2020-2021.pdf · uploaded 23 Sep 2022View
  • b Details of encumbrances concerned to LegalEncumbrace Certificate.pdf · uploaded 23 Sep 2022View
  • Disclosure of sold/ booked inventoryArchitect's Certificate Form 4.pdf · uploaded 23 Sep 2022View

Promoter documents

  • Declaration Form B6.pdf · uploaded 31 Jul 2017View
  • Legal Title report1.pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout Approval3.pdfView
  • Building Plan Approval9.pdfView

Proforma allotment letter

  • Proforma allotment letterProforma - Allotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Wardha (M Cl), Wardha taluka

Survey, CTS, gat or plot numbers

566Plot No 5

As published on MahaRERA's project page

Plot No 5,6

Boundaries

North
Plot No 12-13
South
18 Metre Road
East
Plot No 4
West
Plot No 7

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVikas L Golait—
Chartered accountantDeepak N Bhutada—
EngineerVikas L Golaitit—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology