Dwarka City

Completed

Nagthana, Wardha 442001 |Promoter: Deepak G. Mandokar And Rahul M. Sharma

28 May 2018Registered with MahaRERA
30 Dec 2021Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Completed
Land area for this project
4,317 sq m (46,464 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
817 sq m (8,792 sq ft)
Address
Survey No 72/1, Nagthana, Nagthana WardhaPIN 442001
Designated bank account
Axis Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.73640, 78.55190
Dwarka City is at latitude 20.73640, longitude 78.55190.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2021

The latest completion date on record passed 4 years and 10 months ago.

Registered
28 May 2018
Promised
30 Dec 2021

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5040001662928 May 201830 Dec 2021—Deepak G. Mandokar And Rahul M. SharmaProject page

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsTar Road100%
  • Internal Roads & FootpathsTar Road100%
  • Water SupplyBorewell100%
  • Water SupplyBorewell100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsCement Concrete Drains100%
  • Storm Water DrainsCement Concrete Drains100%
  • Landscaping & Tree PlantingTree With Tree Garut100%
  • Landscaping & Tree PlantingTree With Tree Garut100%
  • Street LightingStreet Light100%
  • Street LightingStreet Light100%
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingSoakpit in Open Space100%
  • Water conservation /Rain water harvestingSoakpit in Open Space100%
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationTransformer With Electric Line's100%
  • Electrical meter room, sub-station, receiving stationTransformer With Electric Line's100%
  • Aggregate area of recreational Open SpaceCompound Wall100%
  • Aggregate area of recreational Open SpaceCompound Wall100%
  • Open ParkingNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

13 documents held by Deedo, 18 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificate

Form b

Allotment letters

Form 4s

Form 5

Registration certificate

Others

Layout plan

Document library

  • Copy of the legal title reportSearch Report (Title).pdf · uploaded 23 May 2018View
  • Details of encumbrancesEncumbrance Certificate.pdf · uploaded 23 May 2018View
  • Copy of Layout Approval (in case of layout)MAP.pdf · uploaded 23 May 2018View
  • Commencement Certificates / NA Order for plotted developmentNA Order.pdf · uploaded 23 May 2018View
  • Declaration in FORM BForm B.pdf · uploaded 23 May 2018View
  • Proforma of Allotment letterAllotment letter.pdf · uploaded 23 May 2018View
  • Building Plan Approval (IOD)MAP.pdf · uploaded 23 May 2018View
  • Proforma of Allotment letterAgreement For sale.pdf · uploaded 23 May 2018View
  • OtherOthers.pdf · uploaded 23 May 2018View
  • Certificates of Architect (Form 4)Form 4 - DIPAK MANDOKAR.pdf · uploaded 10 Jul 2018View
  • Certificates of Architect (Form 4)Completion_Cert_Dipak_Mandokar.pdf · uploaded 10 Jul 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 Deepak Mandokar Rahul Sharma.pdf · uploaded 28 Dec 2019View

Promoter documents

  • Legal Title reportSearch Report (Title).pdf · uploaded 23 May 2018View
  • Declaration Form BForm B.pdf · uploaded 23 May 2018View

Technical documents

  • Layout ApprovalMAP.pdfView
  • NA Order for Plotted DevelopmentMAP.pdfView

Other legal documents

Proforma allotment letter

  • Proforma allotment letterAllotment letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nagthana, Wardha taluka

Survey, CTS, gat or plot numbers

72/1Survey No 72/1

As published on MahaRERA's project page

Survey No 72/1

Boundaries

North
Survey No 70-2
South
Survey No 60
East
Survey No 71 and 73
West
Survey No 61-62-63

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNitin Zade—

Source: MahaRERA project page. Contact details are not shown.