Wardha It Park Project

Completed

Barbadi, Wardha 442006 |Promoter: Maharani Paints Private Limited

31 Aug 2017Registered with MahaRERA
31 Mar 2018Promised completion
3Buildings
66Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Completed
Buildings
3
Unit types
Commercial shops, It commercial66 units in all
Land area for this project
18,152 sq m (1,95,390 sq ft)
Permissible built-up area
18,152 sq m (1,95,390 sq ft)
Sanctioned built-up area
13,305 sq m (1,43,213 sq ft)
Recreational open space
1,815 sq m (19,536 sq ft)
Address
H 1PIN 442006
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.76483, 73.61535
Wardha It Park Project is at latitude 18.76483, longitude 73.61535.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2018

The latest completion date on record passed 8 years and 7 months ago.

Registered
31 Aug 2017
Promised
31 Mar 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5040001157331 Aug 201731 Mar 2018—Maharani Paints Private LimitedProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Commercial Block Sco 1220
Commercial Lsc1040
It Tower66

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

66 units registered

Commercial shops · 60 unitsIt commercial · 6 units
BuildingTypeCarpet areaUnits
Commercial Block Sco 1Commercial shops611.6 sq m · 6,583 sq ft20
Commercial LscCommercial shops504 sq m · 5,425 sq ft40
It TowerIt commercial9,904.54 sq m · 1,06,611 sq ft6

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Commercial Block Sco 1Closed/Covered00000
Commercial Block Sco 1Open Space000040
Commercial LscClosed/Covered00000
Commercial LscOpen Space000064
It TowerClosed/Covered00000
It TowerOpen Space000025

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Commercial Block Sco 1

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Commercial Lsc

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

It Tower

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsWBM work completed100%
  • Water SupplyMIDC SUPPLY100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)WORK IN PROGRESS100%
  • Storm Water DrainsWORK IN PROGRESS100%
  • Landscaping & Tree PlantingWORK IN PROGRESS100%
  • Street LightingWORK IN PROGRESS100%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingWORK IN PROGRESS100%
  • Energy managemcntWORK IN PROGRESS100%
  • Fire protection and fire safety requirementsWORK IN PROGRESS100%
  • Electrical meter room, sub-station, receiving stationWORK IN PROGRESS100%
  • Aggregate area of recreational Open SpaceWORK IN PROGRESS100%
  • Open ParkingWORK IN PROGRESS100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

18 documents held by Deedo, 25 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificate

Form b

Form 1

Form 5

Registration certificate

Completions

Others

Layout plan

Building plan

Allotment letter

Document library

  • Copy of the legal title reportauthenticated Lease Agreement.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesself Certification- no Ecumbrances.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)Sanction Plan- Drawings.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BForm B Declaration.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate - (Form 1).pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterProforma of Allotment letter.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)Sanction Plan.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Form 2.pdf · uploaded 31 Jul 2017Source
  • Certificates of CA (Form 5)CA Certificate ( Form 5).pdf · uploaded 31 Jul 2017View
  • OtherBuilding_Plan_approved_Letter.pdf · uploaded 31 Jul 2017View
  • OtherAuthorization Letter.pdf · uploaded 31 Jul 2017View
  • OtherOccupancy Certificate-(1).pdf · uploaded 26 Feb 2018View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentForm 4 New Format.pdf · uploaded 30 Jun 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentForm 4 Architect's Certificate Wardha IT Park Project.pdf · uploaded 30 Jun 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentWardha IT Park Form 4 Architect Certificate R2.pdf · uploaded 6 Jul 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Phase-1 Jul 10, 2023 12-47 PM.pdf · uploaded 12 Jul 2023View

Promoter documents

  • Legal Title reportauthenticated Lease Agreement.pdf · uploaded 31 Jul 2017View
  • Declaration Form BForm B Declaration.pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout ApprovalSanction Plan- Drawings.pdfView
  • Building Plan ApprovalSanction Plan.pdfView

Other legal documents

  • OtherOccupancy Certificate-(1).pdfView
  • OtherBuilding_Plan_approved_Letter.pdfView
  • OtherAuthorization Letter.pdfView

Proforma allotment letter

  • Proforma allotment letterProforma of Allotment letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Barbadi, Wardha taluka

Survey, CTS, gat or plot numbers

H 1

As published on MahaRERA's project page

H 1

Boundaries

North
Plot No R 1 Zudpi Jungle
South
Midc Plot No H 2
East
Midc Boundaries
West
Cart Tract

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNishit Gupta—
EngineerYashpal Singh—
OtherAshok Omprakash Mittal—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology