Skip to content

New Suraj Tower

Certificate Signed

Vartaknagar, Thane 400602 |Promoter: Ekdanta Constructions and Developers

Residential / Group HousingRERAP51700015400
21 Feb 2018Registered with MahaRERA
30 Dec 2023Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Address
206/1 Part, Vartak Nagar, ThanePIN 400602
Designated bank account
171
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.20826, 72.96101
New Suraj Tower is at latitude 19.20826, longitude 72.96101.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2023

The latest completion date on record passed 2 years and 10 months ago.

Registered
21 Feb 2018
Promised
30 Dec 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001540021 Feb 201830 Dec 202330 Dec 2023Ekdanta Constructions and DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
New Suraj Tower31—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

1 document held by Deedo, 36 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportTitle Report.pdf · uploaded 30 Jan 2018Source
  • Declaration Form BForm B - Declaration New.pdf · uploaded 12 Feb 2018Source
  • OtherSBI Sanction letter.pdf · uploaded 7 Jun 2020Source
  • OtherNST OC.pdf · uploaded 28 Nov 2022Source

Migrated

  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 30 Jan 2018Source
  • 1 Details of encumbrancesencb_certificate-min.pdf · uploaded 30 Jan 2018Source
  • 1 Building Plan Approval (IOD)Commencement Certificate.pdf · uploaded 30 Jan 2018Source
Show all 37 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 30 Jan 2018Source
  • 1 Proforma of Allotment letterallotment_letter_RERA_Format-min.pdf · uploaded 30 Jan 2018Source
  • 2 Proforma of Allotment letterDRAFT AGREEMENT SALE-min.pdf · uploaded 30 Jan 2018Source
  • 1 Copy of Layout Approval (in case of layout)SANCTION PLAN 12022018.pdf · uploaded 12 Feb 2018Source
  • 1 Declaration in FORM BForm B - Declaration New.pdf · uploaded 12 Feb 2018Source
  • 1 Certificates of CA (Form 3)CA_Certificate 06-02-18.pdf · uploaded 14 Feb 2018Source
  • 3 Proforma of Allotment letterDRAFT SALE AGREEMENT.pdf · uploaded 11 Oct 2019Source
  • 4 Proforma of Allotment letterDRAFT SALE AGREEMENT.pdf · uploaded 11 Oct 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 6 Jun 2020Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 6 Jun 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate.pdf · uploaded 6 Jun 2020Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate.pdf · uploaded 6 Jun 2020Source
  • 2 Certificates of CA (Form 3)Charted Account.pdf · uploaded 6 Jun 2020Source
  • 1 OtherSBI Sanction letter.pdf · uploaded 7 Jun 2020Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect.pdf · uploaded 9 Jun 2020Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect.pdf · uploaded 9 Jun 2020Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engeener.pdf · uploaded 9 Jun 2020Source
  • 3 Certificates of CA (Form 3)VB waghmare CA.pdf · uploaded 9 Jun 2020Source
  • 4 Certificates of CA (Form 3)VB waghmare CA.pdf · uploaded 9 Jun 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 FY 18 19.pdf · uploaded 10 Feb 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 FY 19 20.pdf · uploaded 10 Feb 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FY 20 21.pdf · uploaded 10 Feb 2022Source
  • 2 OtherNST OC.pdf · uploaded 28 Nov 2022Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)2022-11-23_CERTIFICATE OF COMPLETION WORK NST BLDG NO 35.pdf · uploaded 15 Nov 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2022-11-09_FULL OCCUPANCY CERTIFICATE_ECD_VN35 (2).pdf · uploaded 15 Nov 2024Source

Technical

  • DocumentCommencement Certificate.pdf · uploaded 30 Jan 2018Source
  • DocumentSANCTION PLAN 12022018.pdf · uploaded 12 Feb 2018Source

Technical (Architect)

  • DocumentArchitect.pdf · uploaded 9 Jun 2020Source

Technical (Engineer)

  • DocumentEngeener.pdf · uploaded 9 Jun 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Vartaknagar, Thane taluka

Survey, CTS, gat or plot numbers

206/1 Part

Boundaries

North
40m wide DP Road
South
12m wide Internal Road
East
Building No 34
West
Building No 36

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDesign Consortium Architect I Private Limited—
OtherNath Paint art—
OtherRahul Enterprises—
OtherSky Scraper Eng & Contractors—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology