Building No 5 · Shankheshwar Crystal-Phase 1
Titwala · RERA P51700000463
IDBLD_0494119 floorsPromised date passed
9Sanctioned habitable floorsregistration certificate
31 Dec 2018Revised completionpromised 31 Dec 2018
19 of 62Units bookedMahaRERA project page
Floors
9 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P51700000463 · registered 18 Jul 2017
- Promised completion
- 31 Dec 2018
- Revised completion
- 31 Dec 2018
- Sanctioned habitable floors
- 9
- ProjectId
- 5,337
- ProjectName
- SHANKHESHWAR CRYSTAL-PHASE 1
- TotalUnitCount
- 0
- ProjectBuildingId
- 2,047
- BuildingNameNumber
- BUILDING NO 5
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P51700000463
- ProjectBuildingWingsId
- 2,047
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- BUILDING NO 5
- NoOfBuildingWingFloorProposed
- 9
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 9
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 30.6 m² (330 sq.ft) | 46 | 16 |
| 2 BHK | 44.2 m² (475 sq.ft) | 16 | 3 |
| Total | 62 | 19 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology