Building 05 · Padamavati Royal Phase 1

Titwala · RERA P51700023535

IDBLD_0699428 floorsPromised date passed
8Sanctioned habitable floorsregistration certificate
28 Nov 2025Revised completionpromised 28 Nov 2025
43 of 46Units bookedMahaRERA project page

Floors

8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51700023535 · registered 18 Dec 2019
Promised completion
28 Nov 2025
Revised completion
28 Nov 2025
Sanctioned habitable floors
8
ProjectId
29,833
ProjectName
Padamavati Royal Phase 1
TotalUnitCount
0
ProjectBuildingId
24,611
BuildingNameNumber
Building 05
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P51700023535
ProjectBuildingWingsId
24,611
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Building 05
NoOfBuildingWingFloorProposed
8
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
8

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK29.7 m² (320 sq.ft)4643
Total4643
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology